Easy understanding of office strong and weak current Integrated Wiring Construction

Source: Internet
Author: User

Easy understanding of office strong and weak current Integrated Wiring Construction

Office decoration and office decoration office strong and weak current wiring construction can be divided into four categories: Fixed Point, slotted, wiring, sealing trough, etc.

1. determine the point

1. The basis for determining the position: According to the office space wiring design drawing, combined with the office work station, use a pencil, ruler or ink bucket to mark the position of the hidden box.

2. determine the height of the hidden box: Except for special requirements, the height of the hidden box is the same as that of the original strong electrical outlet, and the height of the background music tuning switch should be the same as that of the original strong electrical switch. If multiple hidden boxes exist together, the distance between the hidden boxes should be at least 10mm.

3. determine the location of the cabling box:

1) embedded layout: increase the size of the Weak Current Wiring box by 10mm for each of the widths and heights, and decrease the size by 10mm for the depth direction.

2) External: Mark the position of the fixed hole according to the model size of the product used.

3> internal: determine the height of the product to which the pipeline enters.

Ii. Slotted

1. Determine the slotted route according to the following principles:

1) Principle of shortest route;

2) do not undermine the original strong electricity principle;

3) do not damage the waterproof principle.

2. Determine the slotted width: determine the number of PVC pipes based on the signal line, and then determine the width of the slot.

3. Determine the groove depth: If 16mm PVC pipe is selected, the groove depth is 20mm. If 20mm PVC pipe is selected, the groove depth is 25mm.

4. Cable trough appearance requirements: horizontal and vertical, uniform size.

5. Groove measurement: The dark box and the distribution box groove are calculated independently. All groove are measured from the start point to the end point of the groove. If the width of the groove exceeds 80mm, the length of the two groove is calculated.

3. Wiring

1. confirm that the cables are smooth:

1) cable and telephone line tests: Separate the crystal head and use the network tester to test the disconnection;

2) cable TV line, audio/video line, and audio line test: Use A multimeter to test the disconnection;

3> other cables: Use the corresponding professional instruments to test the disconnection.

2. determine the length of each point line:

1) measure the length from the distribution box slot to each point;

2) The length of the redundant lines at each point and the distribution box slot is 200-300mm, and the length of the line in the distribution box is 500mm, exit of Background Music: The line length ranges from 1.5 to 2.

3. Confirm the labels: after each cable is cut down to a certain length, the two ends of the line are labeled separately, and the weak current type-room-serial number is specified.

4. determine the number of lines in the pipe: the cross-sectional area of the tube must not exceed 80% of the cross-sectional area of the tube.

Iv. Sealing Slot

1. Fixed dark box: in addition to the kitchen and bathroom dark box, the wall should be protruding 20mm, and other dark boxes should be flat with the wall. When several hidden boxes are together, they must be on the same horizontal line.

2. Fixed PVC pipes:

1) the ground PVC pipe must be fixed every one meter interval;

2) The PVC pipe of the trough must be fixed every two meters;

3) The wall trough PVC pipe must be fixed at intervals of one meter.

3. Groove sealing: the wall and ground after the groove sealing must not be above the plane.

4. Cleaning construction site: After the sealing trough is completed, clear the garbage and clean the construction site.

1) Each Weak Current subsystem uses a star structure.

2) line feed pipe threading 2 ~ The three cables are introduced into the data room from the building distribution box, and the pipe passing through the outlets is from the data room to various information points. The Hidden pipes (pipe passing) shall adopt steel pipes or flame retardant rigid polychloroethylene pipes (rigid PVC pipes ).

3) The pipe diameter utilization rate should be 50% ~ 60%, the pipe diameter utilization rate of the bend is 40% ~ 50%.

4) steel pipes should be used when local interference sources exist on the cabling Road and cannot meet the minimum net distance requirement.

5) when the laying length of the hidden pipe is over 30 meters, a wire transfer box should be installed in the middle.

6) when the Hidden pipes must be bent and laid, the routing length should be less than or equal to 15 meters, and there should be no S bending in the Section. When bending for more than two consecutive times, a wire transfer box should be installed.

7) the bending radius of the hidden tube shall not be less than 6 to the outer diameter of the tube ~ 10 times.

8) There shall be no cables or connectors in the hidden pipe hole.

Contact Us

The content source of this page is from Internet, which doesn't represent Alibaba Cloud's opinion; products and services mentioned on that page don't have any relationship with Alibaba Cloud. If the content of the page makes you feel confusing, please write us an email, we will handle the problem within 5 days after receiving your email.

If you find any instances of plagiarism from the community, please send an email to: info-contact@alibabacloud.com and provide relevant evidence. A staff member will contact you within 5 working days.

A Free Trial That Lets You Build Big!

Start building with 50+ products and up to 12 months usage for Elastic Compute Service

  • Sales Support

    1 on 1 presale consultation

  • After-Sales Support

    24/7 Technical Support 6 Free Tickets per Quarter Faster Response

  • Alibaba Cloud offers highly flexible support services tailored to meet your exact needs.