About data center selection and use of elevated floors there are many things to think about, you decide to use elevated floors, most of the time you are your own layout and maintenance, the following steps will help you determine the investment.
Elevated floor layout
If you cannot access electrical, mechanical, and other infrastructure under elevated floors, the elevated floors are not paved, so it is important to align the racks and cabinets with the floor line.
Any overlapping floors cannot be removed, if there is an important facility underneath it is very bad, but this is still very small, the National electrical specifications require electrical power outlets and protection boxes to be exposed for use, the best way is cable bridge and cooling water pipe should also be seen, because in the inspection of cables, When valves or repair leaks, you do not want to move cabinets filled with servers, switches, disk storage, and other IT devices.
Figure 1 alignment of the rear of the cabinet with the floor line provides more space for the front mounted device
A unified cabinet or rack is usually aligned with the back edge of the floor cut line, if the cabinet is 24 or 48 inches deep, it can be aligned with the United States standard 24 square inch floor, the metric cabinet usually fits 600 square millimeters of floor, but when used in 36 or 42 inch cabinets, The floor line and the rear of the cabinet can provide more space for the front mounted device, as shown in Figure 1, because many modern servers and switches are very deep, and leaving a certain amount of leeway is not only useful, but also necessary for server lift devices (such as rails).
&http://www.aliyun.com/zixun/aggregation/37954.html ">nbsp; Figure 2 48-inch cabinet can overlap with floor line, alternately, install more flexible
On the other hand, 48-inch cabinets are becoming more and more popular, because the size of the equipment and cable volume is also growing, they are designed for very deep hardware, need more front-end space, the best way is to build three floors (or 6 feet) wide cold channel, for more airflow to provide space for refrigeration, You can also use the two layouts shown in Figure 2, but you can only save 2 feet per 38 feet, so there's no need to do that unless your data center is very large.
One of the most important aspects of floor layout is to determine its best position in the room floor grid, the data center designers will usually on the construction drawings with some fixed points as reference point of the elevated floor, such as centerline, but this may not be the most efficient use of space design, on the contrary, It is more practical to plan the cabinet depth and aisle width based on the floor grid, deploy the device on the grid, then adjust the entire plan and the floor grid to achieve the best aisle spacing, and you may even be able to make room for the rooms to install a row of cabinets.
For cabinets, cable tray, lighting, air-conditioning and piping, electric busbar or wire pipe in a room, whether it is from the elevated floor from the beginning or the height of the floor grid size, this is very important, elevated floor grids should be in advance (in the construction industry is called the site conditions), In order to avoid the actual construction of the size deviation, will not cause the related component dislocation, for example, if the wall moved a few inches, everything in the room to follow its move to remain aligned.
The content source of this page is from Internet, which doesn't represent Alibaba Cloud's opinion;
products and services mentioned on that page don't have any relationship with Alibaba Cloud. If the
content of the page makes you feel confusing, please write us an email, we will handle the problem
within 5 days after receiving your email.
If you find any instances of plagiarism from the community, please send an email to:
info-contact@alibabacloud.com
and provide relevant evidence. A staff member will contact you within 5 working days.