Team members: Chen Shuyun, Yang Jiane, Chen XiTeam selection: Primary arithmetic AppThird Sprint stage time: 12.12~12.22This release is the music playback function, can play music according to user needs while doing the problem, but also has a pause to play the music function, enhance the practicality of the appMainactivity.java:Package Com.example.calculator;import Android.os.bundle;import Android.app.activity;import android.content.Intent; Import An
1. Start a new sprint:Starting and ending: 2016.6.1~2016.6.14
Product Backlog: Continue down refinement
Sprint Planning meeting: Determine the goals to be completed for this sprint
Sprint Backlog: What to do with a new sprint
Mission claim
Sprint Cyc
1. Start a new sprint:Starting and ending: 2016.6.1~2016.6.14Follow the procedure below
Product Backlog: Continue down refinement
Sprint Planning meeting: Determine the goals to be completed for this sprint
Sprint Backlog: What to do with a new sprint
Mission claim
1. Start a new sprint:Starting and ending: 2016.6.1~2016.6.14Follow the procedure below
Product Backlog: Continue down refinement
Sprint Planning meeting: Determine the goals to be completed for this sprint
Sprint Backlog: What to do with a new sprint
Mission claim
1. Start a new sprint:Starting and ending: 2016.6.1~2016.6.14Follow the procedure below
Product Backlog: Continue down refinement
Sprint Planning meeting: Determine the goals to be completed for this sprint
Sprint Backlog: What to do with a new sprint
Mission claim
3.0-----------------------------------------------------Steps of the SCRUM process 2:spring plan1. Make sure the product backlog is organized.2. Sprint cycle, a sprint cycle, length of two weeks, this semester also has three sprint cycle.3. Determine the sprint target.3.1 The product owner summarizes the product backlo
the use cases.1. Typical users can include: Name, age, income, the proportion and importance of the users on the market, the typical use of the software , the use of the Software/service environment, Life /work status, knowledge level and ability, user motivation, user preferences. 2, the main steps of the function-driven design are:(1) Construction of the overall model (Develop an Overall models);(2) Construction function list (build a Feature list)
The two week of the second sprint officially ended today, with half of the 4 sprint plans in the past.Overall, Sprint 2 plans to complete 4 of the user story and actually completes 3 of them:
Save ASC Art in server and generate ASC Art Gallery
Generate dynamic ASC art from GIF
Generate ASC Art based on WX ' s default sticker
User Story 1 not
Original Mike CohnHow do I get back to the meeting? Different teams, everyone's approach may be different. I would like to introduce one of my favorite ways, especially since this method has withstood the test of time, and for many years I have used it in many, many teams.Start/stop/ContinueI like to ask team members at a sprint review Meeting 3 questions: What do they want to start? What do they want to stop doing? What do they want to do? This type
My-hr
Members:
Role Assignment
School Number
Blog Park
Team Contribution points
Khuhuhimin
PM Project Manager
201406114203
http://www.cnblogs.com/qiuhuimin/
21st
General Ming Yin
User
201406114204
http://www.cnblogs.com/mingyin/
22
Wolf
Product Owner
201406114227
http://www.cnblogs.com/range/
19
Candidly
Scrum Master
201406114229
htt
Goal of the first sprint: to achieve basic tasks and lay the groundwork for a second phase of sprint
The first stage sprint actually completes the task: has basically achieved the sprint target, but the existence of the shortcut key conflict problem unresolved, did not realize the corresponding function related to t
Date
Work today
Difficult
Tomorrow
Sprint 4
To write a query design
Spend time using native time application
Tomorrow: Query data to solve the local time application, time sorting output classification record
Sprint 5
Query data to solve the local time application, time sorting output classification record
Failed to complete
Query data
topic: "What have we done in this sprint?" What's the next plan? "
Sprint Summary: In this sprint, this is the first time members of our team started a team project development in the form of a team, as early as the first team meeting, we had a long time because of the problem of the team topic, after 2 discussions to finalize our current topic-the invit
A product backlog is a list of tasks that are broken down according to the initial requirements, including all functionality that is functional and non-functional, prioritized by the product owner for the task in the product backlog, and when the development team starts a task, the task is precisely defined and decomposed.The product backlog is the master of all the features that a product needs to have. When a project is just beginning, no one can foresee all the tasks and requirements beforeha
possible to confirm the signature of the certificate, profile is not their own designation.Distribution of IPA documents in betaThere are 3 main ways to distribute IPA documents to testers in beta:
Use itunes to sync the IPA to your phone;
Download and distribute using the Itms-services protocol;
Use third-party tools for download distribution.
Please note that no matter what form of distribution is used, the limit on the number of people in the beta and the udid limits of
team blog
team GitHub
Third sprint questions and suggestions
hgf520
Regionalcrimeunit
Server version cannot order
xjy-gg
goidenbubble
Upload the app to the store.
liezhihua
LWHTF
Upload the app to the store, Burndown chart with tools
caicaihong
RaiCai
github commit record too little,
deadline:2015-11-07 8:00amThis team work will last two weeks, complete the alpha version of the project, and demonstrate in the 2015.11.07 practice session.Read or re-read the building Act to help with the scheduling and problems of the project sprint.1, in a period of two weeks, scheduled sprint 10 days. Stand-up meetings are held every day to discuss the progress of each member of the project yesterday, t
First, wealth management cat:1, the dark part of the interface, the font should be adjusted to bright colors, you can properly beautify the font.2, want to be able to automatically record expenses, instead of only manually "remember a pen".3, slightly less function, such as can add "income details", "expenditure details".Second, run what to exercise:1.2.3.Three, Water knight:1. We hope to solve the problem of unable to login as soon as possible.2, the registration is successful, return to the in
School:Questions:1, add new Note function If you can classify, or add a tag is good.2, add notes, you should be able to add a memo function (Reminder function).3, see left now only four items, hope to finally not only have these several, to the note more function, service students.Reply:We will gradually add these features later, thank you13. Library AssistantsQuestions:There is a large space on the top of the homepage can add something. What is your
Demand Analysis: Tea industry Management system is a product-employee integrated management system.Employee Management: Set up different positions and have different access rights for different positions. Employees can only sell goods, the Treasurer only to view the inventory of the goods and merchandise sales records; The company owner is able to view all the information ...Commodity management: The Classification of goods management, the increase and deletion of the search ...Performance manag
The content source of this page is from Internet, which doesn't represent Alibaba Cloud's opinion;
products and services mentioned on that page don't have any relationship with Alibaba Cloud. If the
content of the page makes you feel confusing, please write us an email, we will handle the problem
within 5 days after receiving your email.
If you find any instances of plagiarism from the community, please send an email to:
info-contact@alibabacloud.com
and provide relevant evidence. A staff member will contact you within 5 working days.