Stand -up meetings are the members of each other who stand up to each other and say their progress, not meetings, not writing reports. is for better communication and coordination, essentially for engineering team communication.The requirements for the scrum stand -up meeting are as follows:1. Members are equal, and statements do not differ between managers and programmers, and everyone needs to keep their statements within 15 minutes.2. The content o
5.0---------------------------------------------------1. Team members complete the tasks they claim. 2. Burndown Chart: Understand, design and draw the ideal line of the Burndown chart for this sprint. Refer to Figure 6.3. The Daily schedule updates the task completion on the task board, the actual line of the Burndown chart, and analyzes whether the project progress is on track.At the end of each day, the task board is photographed and posted on the blog. 4. See progress every day and be contin
Team Name: √3Team Goal: Fully complete this projectTeam slogan: I want to change the world, change myself!!!Speech: Our product selection of chicken soup is to solve the current social emergence of too much negative energy to make people's hearts very painful, they need a strong positive energy to soothe their dark heart, but the existing solutions do not solve these needs well, we have a unique way to remember the chicken soup, there must be something you would like to drink, it can bring benef
Because the time to deploy is near, and we are slow to progress. This evening, most of our members spent almost all of their time on this project, and the results were satisfactory.
Members
Mission today
Time
Tomorrow mission
Fu Mei Xiao
1. Fixed a bug that caused the number of pages crawled to be larger than the number of pages requested by the user.2. The database manipulation functions that generate pie charts based on data in the database ha
Product introduction
Sprint1
Sprint2
Sprint3
Our product "micro-vision" is to provide a resource for the public numberPlatform for the vast number of film enthusiasts.Make it easy for them to find the movies they need,No worries, safe high-definition convenient is our purpose
Set up the public number, make the interface good,Get ready to add links later(Imp:20 Est:3)
1. Learn Nodejs and database knowledge, familiar with its principles(imp:40 est:5)2. Use Nodej
Task Schedule
Members
Completed today
Tomorrow mission
Yan
Database operation to complete the learning progress record
Database operation to complete the learning progress record
Bin Tang
Writing code to interact with the server
Writing code to interact with the server
Shi Xuan
Get Video URL
Yu Fan
Acquisition of local paths
Acquisition of local paths
Progress:Dongminlong: The ability to successfully implement voice input based on the Oxford Speech API, but due to the limited number of accesses to the server (6 times per minute), this feature is not ready to be added to the alpha version;Yandongzhaoyang: Complete the front-end interface configuration of automatic labeling function;Fuchen:release Note information collection;All: At noon and Lily, Qiufeng opened a short meeting, deeply aware of the previous project in a lot of deficiencies, suc
UI
1
Add a percentage of course progress
2
Add Course video Download Portal
1
Bin Tang
Read iOS code + read the last network core code
1.5
!
Server interaction
1.5
Server Data analysis
3
List of discussion areas
1
Discuss post details
2
Post reply
Meeting MinutesThe backend is basically complete, ending the current Sprint, start the next sprint. The UI is discussed further, and task assignments are completed. BurndownProgress
Part
Crew
Work today
Time (h)
Daily Plan
Time (h)
Wei
Renqian
Chongyang
Shuo
Daily
familiar with how it works.
After today due to a week or so away from the defense, we should have the following preparations for this week:1. Let the new crawler deployed on the server crawl as many URLs as possible to get more data.2. Put together some of our new features and solve the bug, ready to use the reply.3. All members test the software and make some fine-tuning if the problem is found.4. Find time to make a final summary of the Conference and make a final cont
Task Schedule
YanComplete today: Design the local database.Tomorrow task: leave. (Recent code is much more ...) Tired...... )Bin TangCompleted today: Understanding of iOS client code.Tomorrow task: Deep learning for iOS client code.Shi Xuan:Completed today:Tomorrow's Mission:Yu Fan:Completed today: Understanding of the Server interface.Tomorrow task: Deep learning for server interfaces.Kim Yong:Complete today: Read BUAAMOOC completed code.Tomorrow's task: Learn and learn about the UI modificat
1. Prepare the Kanban board.
Form reference Figure 4.
2. The task is claimed and the claimant is marked on the task label on the Kanban board.
First by the individual initiative to lead the task, PM according to the specific situation of the task balance.
Then everyone embarked on the task of achieving their own.
3. For team work Happy progress, please adhere to the daily meeting.
Set the time and place for the daily meeting.
Photo photos (At least once, posted to
One, team member task completion situation
First page design completed but need to optimize the interface, only simple output information and login on the homepage. The interface is extremely simple.
Chicken Soup Layout design is difficult, the question is what form to manage the user's data upload, but after the discussion between the group to determine the design direction of change, the main design restart, the expected progress slowed down, need to be responsible for other inter
One, team member task completion situation
First page design completed but need to optimize the interface, only simple output information and login on the homepage. The interface is extremely simple.
Chicken Soup Layout design is difficult, the question is what form to manage the user's data upload, but after the discussion between the group to determine the design direction of change, the main design restart, the expected progress slowed down, need to be responsible for other interface
Scrum TeamTeam situation:Team Name: @four!Team Blog Address: http://www.cnblogs.com/gjpg/team GitHub Address: https://github.com/ganjiapingTeam members:Team member 1 Study No.: (Group leader) 201406114207 name: Gan Jiaping personal blog Link: http://www.cnblogs.com/gjpg/personal github Link: https://github.com/ganjiapingTeam members 2 School number: 201406114224 name: Allen Lee personal blog Link: http://www.cnblogs.com/l549023320/personal github Link
for daily meetings. Each student records the implementation of their own tasks, can be posted on their own blog.This blog deadline: 2016.5.17 7 o'clock in the evening. 1. Kanban design and the detailed figure of the persona claim Task 2. Daily meeting time and location time: 17:00 Location: Dormitory door Daily meeting Report summary: In this meeting, we mainly discussed how to better and more efficient to achieve a good job of each of our spring plan, the implementation of the Web version we
Everyone's task is being carried out in an orderly manner today.One of the surprises was the last time Lin Xupeng changed the code on the server because the server was restarted and had to be written again.Everyone for this software is also pretty spelling. Constantly discovering new problems and constantly changing them. This is the morning chat record.Here are our tasks:
Name
Mission today
Liu Xinpeng
Fixed an issue with SQL language database and softw
Complete the task today:Complete the optimization of the algorithm for the resource display on the right side of the homepage, and resolve the exception when downloading the resource.
Difficulties encountered:Compiling this week to check, the team members of most of the time to complete the compilation of the course set, time is very tight.
Tomorrow's Mission:
Sun Siquan
Complete the second set of provided database interfaces
Feng fluttering
Perfect
View
Shilin Liu
Design Death Treatment
Yiming Liao
Handling tank-Bullet Collision Events
Server
Songtao He
Fix bug when bullet queue is full
Junbei Zhang
Server Quorum tank Death event
Jiafan Zhu
The total decline is to sort out a bug that doesn't need to be fixed at the current stage [ase][daily scrum]
After the 11th holiday, everyone is back and scrum is about to start again.
Today's work
Tomorrow's work
Note
Lin Meng
Activity search
Participate in activities
Lin Meng made a pending example for your reference.
Chen Xiaomeng
Movie search framework
Complete movie search
Li minglei
Obtain the details of a bean mail.
Send bean mail (get list)
The content source of this page is from Internet, which doesn't represent Alibaba Cloud's opinion;
products and services mentioned on that page don't have any relationship with Alibaba Cloud. If the
content of the page makes you feel confusing, please write us an email, we will handle the problem
within 5 days after receiving your email.