A Sprint plan meeting is held on the first day of the sprint. This meeting is divided into two parts. Plan meeting 1 is attended by Po, Sm, and team, it is mainly to select the established product backlog that needs to be placed under the current sprint from the product backlog, and then the SM and team participate in the planning meeting 2, split the story of th
Introduced:
For Agile Software Development, it is important to keep track of the progress of the project at all times, as you can keep abreast of the health of the team and deal with unexpected situations in a timely manner to ensure that our projects are delivered on time after each iteration.
Implementation mode:
The best tool to see the project progress is of course Burndown chart, we use Jira to do project management tools, Jira has a view of the show, can very intuitive display story bur
The Sprint planning meeting was held on the first day of the sprint, and the meeting was divided into two parts, with the Plan meeting 1 being attended by PO, SM and team, mainly from the product backlog to select the backlog of products that need to be placed in the current sprint, and then by SM, Team participated in the program meeting 2, the story of the back
design, including login registration interface, product information interface, user feedback interface and so on, it takes about 30 hours of working timeGroup Chen Zhili: Background management, including the establishment and connection of the database, the update of the quantity of goods, it takes about 20 hoursGroup One: Further market research and user demand analysis, takes about 15 hours of timeCrew Zhao Yonghen: Software Testing and maintenance takes about 8 hoursV. Daily STANDING meeting
Time
Date
Place
Job
18:40
5.21
Nine real
Integrated Network Assistant!
6:49
5.22
~
Change Solution Integration!
Difficulties encountered: Last night, the integration of the pie failed, many of the problems were never thought before. Think that the class are added to the new project, the Lib package is directed in, draw a new interface with the original ID value, and then build on the line. This morning can only
part of the sixth assignment according to the progress of the project
Learn the UML Diagram and the building method to learn about the tools required for blogging and design.
problems encountered: a database field with a length exceeding the limit error causes an insert exception, and some hidden bugs require multiple tests to discover. When you join a group, the request fails, and there is no error returning information that needs to be parsed from the logical layer of the code.
Complete and publish Summary blog, sixth chapter of building Law, learning UML diagram
Wu Jingan
Unit testing of completed functions
Improve the test results of completed functions, design test cases for the function of the next step plan implementation of the meeting
Hu Zhiquan
Complete part of the sixth assignment according to the progress of the project
Learn UML diagrams, Learn the tools your blog and design requires.
problems
In the agile development framework of scrum, the most important part is the Sprint plan meeting. If the meeting fails, the whole sprint will make the scrum team suffer and it is difficult to complete the initial sprint goal. After several attempts, we finally found our own model. These methods and principles are the best for us. Based on our own knowledge and our
Note: The Development Management Checklists-series of articles are transplanted from my iteye blog. The Development Management checklists column will be updated directly in the future.
This article mainly aims to check your understanding and usage of the scrum Sprint plan meeting,
Through this article, you can check1. process and steps of your scrum Sprint plan MEETING2. output results of the MeetingSprint
intended to be used by customers, acting as a consumer, feedback product information4.master: Liang, ensure the team is scheduled to complete the mission semesterSemester Sprint Time:November 4-December 18First Sprint goals and assignments:1. Register login screen claim: Wang Dahua2. Interface Jump CLAIM: Liang3. Ordering interface Claim: Feng Zifan4. Payment interface Claim: Jongjie5. Management interface
team blog
team GitHub
Second sprint questions and suggestions
hgf520
Regionalcrimeunit
xjy-gg
goidenbubble
No jobs submitted for the second sprint
liezhihua
LWHTF
No project progress control, blog/github follow up not in time
caicaihong
RaiCai
In my previous introduction, I described the relationship between release, sprint, and story. Reference: several meetings in scrum management and our practices
To put it simply, a release can include several sprints, and a sprint contains several story. Of course, a story can span multiple sprints or release. But what about the version? In practice, we need to use the GIT tag pairCodeTo ensure that all th
1. Start a new sprint:Starting and ending: 2016.6.1~2016.6.14Follow the procedure below
Product Backlog: Continue down refinement
Sprint Planning meeting: Determine the goals to be completed for this sprint
Sprint Backlog: What to do with a new sprint
Mission claim
1. Start a new sprint:Starting and ending: 2016.6.1~2016.6.14Follow the procedure below
Product Backlog: Continue down refinement
Sprint Planning meeting: Determine the goals to be completed for this sprint
Sprint Backlog: What to do with a new sprint
Mission claim
Introduced:
One of the first and most important activities for an iterative cycle sprint is the sprint Setup meeting. At this meeting, we will mainly explore some of the story that we need to accomplish in this sprint, and what the specific requirements of these story are. In fact, our company is taking the offshore development model, in which we have a time dif
Original Mike CohnHow do I get back to the meeting? Different teams, everyone's approach may be different. I would like to introduce one of my favorite ways, especially since this method has withstood the test of time, and for many years I have used it in many, many teams.Start/stop/ContinueI like to ask team members at a sprint review Meeting 3 questions: What do they want to start? What do they want to stop doing? What do they want to do? This type
My-hr
Members:
Role Assignment
School Number
Blog Park
Team Contribution points
Khuhuhimin
PM Project Manager
201406114203
http://www.cnblogs.com/qiuhuimin/
21st
General Ming Yin
User
201406114204
http://www.cnblogs.com/mingyin/
22
Wolf
Product Owner
201406114227
http://www.cnblogs.com/range/
19
Candidly
Scrum Master
201406114229
htt
Goal of the first sprint: to achieve basic tasks and lay the groundwork for a second phase of sprint
The first stage sprint actually completes the task: has basically achieved the sprint target, but the existence of the shortcut key conflict problem unresolved, did not realize the corresponding function related to t
topic: "What have we done in this sprint?" What's the next plan? "
Sprint Summary: In this sprint, this is the first time members of our team started a team project development in the form of a team, as early as the first team meeting, we had a long time because of the problem of the team topic, after 2 discussions to finalize our current topic-the invit
A product backlog is a list of tasks that are broken down according to the initial requirements, including all functionality that is functional and non-functional, prioritized by the product owner for the task in the product backlog, and when the development team starts a task, the task is precisely defined and decomposed.The product backlog is the master of all the features that a product needs to have. When a project is just beginning, no one can foresee all the tasks and requirements beforeha
The content source of this page is from Internet, which doesn't represent Alibaba Cloud's opinion;
products and services mentioned on that page don't have any relationship with Alibaba Cloud. If the
content of the page makes you feel confusing, please write us an email, we will handle the problem
within 5 days after receiving your email.
If you find any instances of plagiarism from the community, please send an email to:
info-contact@alibabacloud.com
and provide relevant evidence. A staff member will contact you within 5 working days.