First, the goal
We will develop and test the system, and complete the relevant documentation.
Final submission: (1) system source code; (2) Training report: Requirement Analysis + system design + system implementation + system testing.
Ii. Schedule of Progress
1.12 months 29th (Monday), 3-8 knots
Complete the requirements analysis and system design documentation, and related code.
2.12 months 31st (Wednesday), 1-7 knots
Complete the design of system template and homepage, and implement a function module.
3.1 Months 4th (Sunday), 1-8 knots
Complete the main function module and update the complete documentation.
4.1 Months 5th (Monday), 1-10 knots
Complete the main function module and update the complete documentation.
5.1 months 6th (Tuesday), 1-8 knots
Complete the main function module and update the complete documentation.
6.1 Months 7th (Wednesday), 1-8 knots
Write test plans, requirements, test cases, and complete test execution.
7.1 Months 8th (Thursday), 3-8 knots
Test and fix bugs.
8.1 months 9th (Friday), 1-7 knots
Evaluation and acceptance of practical training
Third, the point of scoring
1. System functions, can form a complete business process, error-free.
2. The training report, accurately describes the development and testing ideas and methods.
1th Day of Training (December 29)