In order to strengthen the vertical and horizontal communication of the project team, ensure that the project information can be reported in a timely manner through various formal channels to reflect the real status and historical information of the project, and enhance the visibility of the project development process.
Project reports are a means of communication and coordination between internal and external managers, users, QA, testers, and technicians. Various forms of reports are used to reflect the project status, risks and problems, resource coordination, work summary, and work task arrangement.
The content and method list of various project reports are defined as follows:
Type |
Content |
Timing |
Developed and submitted |
Recipient |
Weekly personal report |
Individual task completion status this week |
Friday afternoon |
Developers |
Project Manager |
Weekly Project Report |
Weekly work summary Project status this week, including progress, quality, and cost Current problems and risks |
Friday afternoon |
Project Manager |
Project Supervisor, project team members, QA and testing personnel |
QA review report |
QA review and problems found |
After QA review |
QA |
Project Manager |
QA Work Report |
Status of current projects |
End of month |
QA |
QC department manager, General Manager, Technical Department, Project Department |
Test report |
Test Problems Test Summary |
Testing process and after completion |
Test team lead |
Project Manager |
Phase (month) report |
Stage status, including progress, cost, and quality. Current problems and risks Configuration status |
End of Phase |
Project Manager |
Project Supervisor, QC department manager, General Manager, and Technology Department |
System Integration Report |
Summary of integration, including progress, quality, and cost Existing risks and problems and solutions |
End of Integration |
Integration Team Lead |
Project Manager, project supervisor, and Technical Department Manager |
Internal delivery report |
Product Delivery list Product acceptance |
User acceptance stage |
Project Manager and configuration representative |
Project Department, QC department manager, Technical Department |
User Acceptance Report |
Preliminary Acceptance Report Test Run Records B testing status Final Acceptance Report |
Acceptance phase |
Project Manager |
Project Supervisor |
Subcontractor evaluation report |
Sub-contractor qualification Evaluation Sub-contractor capability evaluation |
Outsourcing Selection |
Technology Department |
Project Department, QC Department Manager |
Outsourcing acceptance report |
Record and summary of acceptance by contract |
Outsourcing completed |
Technology Department |
Project Department, QC Department Manager |
Project Summary Report |
Project Summary, including progress, quality, and cost |
When the project is completed |
Project Manager |
Project Supervisor, QC department manager, General Manager, and Technology Department |
Interim problem report |
The project manager defines it by himself. |
Http://blog.csai.cn/user1/15332/archives/2006/6246.html