After creating a list in the test environment, we made unremitting adjustments to verify that we finally made a decent form.
This is the case...
How can we migrate data to a production environment or a formal environment?
I found some materials on the Internet, but all of them are 10 ..
As a matter of fact, 13 is not much different from 10, so we found a solution.
Backup list
Simply put, you can save the list as a template.
First look at the effect
Click "current list"> "list Settings"> "save list as template ".
The "Save as template" page is displayed. Enter the corresponding fields and click "OK ".
Note: If the selected package is selected, the template contains the content ..
Click to go to the list template library. The template we just stored already exists in the library.
In this case, we need to download this template, select the template, and click Download copy in the ribbon button above.
At this time, the preparation work is basically completed. The following will upload the downloaded template to the production environment website.
Upload list
Open the production environment website and click website settings
ClickList template
Click Upload document
The same as the existing template.
After the list template is saved to the database, we create a new list to verify whether it is the same as the one originally designed in the test environment.
Click the website content, add the application, and find the list template (it should be at the end)
Name
Click Project
The same as the test environment !!! This is basically the case for using the entire list backup. Smoke ~
Reference address: http://office.microsoft.com/zh-cn/office365-sharepoint-online-small-business-help/HA101969181.aspx? Redir = 0
SharePoint 2013 list backup usage