How to prepare to start agile-How does iteration 0 work?

Source: Internet
Author: User

?? Everything starts hard!

?? For start-up agility, scheduling a pre-launch phase will be useful for a smooth first iteration. The following is an attempt to explain how to prepare to start agile.

?? Iteration 0 refers to the stage of preparation before the start of agile development, where iteration 1 is not longer than the selected iteration cycle.
For Kanban class practices, if there is no explicit iteration cycle, then the recommendation is no more than 2 weeks, and for convenience, the preparation stage of the Kanban class is still called iteration 0.
(with recommendations-for kanban-like practices, it is still recommended to schedule iterations for retrospectives and periodic forecasts, etc.)

?? The main task of iteration 0 is to build the team and prepare the team work environment, and organize the following specific completion definition entries for the specific transaction.

Minimum requirements for the DoD for iteration 0-must meet
    • Teams are in place, working together, or working in remote and quick contact has been established
    • If you adopt a Scrum team model, the product lead (PO) and scrum master are already in place, have been trained in agile fundamentals, or have read the basics of Agile
    • If Kanban is used, the Kanban builder and the requirement/transaction analyst are in place, the Kanban Builder's salutation may be Kanban Master, and have participated in the Kanban basics training, or have read the basics of Kanban and agile
    • If you use XP or something else, then the appropriate agile and demand analysts are in place, and the agile advocates may be called Agile coaches, project managers, team leaders, etc.
    • The scope of the software system or transaction to be handled is clear, and if it is a new development system or a substantial upgrade, complete the preliminary architecture design
    • Initially build the backlog, if using iterations, provide enough backlog to cover iteration 1, and the backlog is less granular than the iteration cycle can handle, and if Kanban classes are used, provide enough backlog to cover 1 weeks.
    • In the workstation accessories whiteboard set up, physical whiteboard or electronic whiteboard can, using a physical whiteboard, need stickers, whiteboard pens and so on
    • Personal development environment in place, such as Eclipse
    • Configuration management tools in place such as git, SVN, etc.
Recommended requirements for the DoD for iteration 0, sorted by recommended level
    • Convene a team meeting to discuss the 1th draft of the team charter and agree on the basic practice of Iteration 1
    • Team collaboration tools in place, such as Redmine,jira, etc.
    • Team members participate in Agile basic training, or read the basics of Agile
    • Perform initial agile scans to identify high-priority improvement issues
    • Develop a preliminary release plan

How to prepare to start agile-How does iteration 0 work?

Contact Us

The content source of this page is from Internet, which doesn't represent Alibaba Cloud's opinion; products and services mentioned on that page don't have any relationship with Alibaba Cloud. If the content of the page makes you feel confusing, please write us an email, we will handle the problem within 5 days after receiving your email.

If you find any instances of plagiarism from the community, please send an email to: info-contact@alibabacloud.com and provide relevant evidence. A staff member will contact you within 5 working days.

A Free Trial That Lets You Build Big!

Start building with 50+ products and up to 12 months usage for Elastic Compute Service

  • Sales Support

    1 on 1 presale consultation

  • After-Sales Support

    24/7 Technical Support 6 Free Tickets per Quarter Faster Response

  • Alibaba Cloud offers highly flexible support services tailored to meet your exact needs.