third, project time management 1, activity definition, 2, activity sequencing, 3, activity resource estimation, 4, activity duration estimate, 5, schedule plan, 6, progress control; |
1. Activity Definition A series of activities to be performed on the lowest deliverables in the work breakdown structure (WBS), the identification of these activities, and the definition of the activities for the archiving process |
Input |
Tools and Technology |
Output |
1, Enterprise environmental factors 2. Organizational Process assets 3. Project SCOPE specification 4, WBS, WBS Dictionary 5. Project Management Plan |
1. Decomposition 2. Templates 3. Rolling type planning 4. Expert Judgment 5. Planning Components |
⑴ List of project activities ⑵ Activity List Properties ⑶ Milestone List Changes initiated by ⑷ |
2, the activity sort: The activity sort also is called the work sort, namely determines the dependence between the activities, forms the document. |
Input |
Tools and Technology |
Output |
1. List of activities, that is, the result of the activity definition process 2. Activity List Properties 3. Project SCOPE specification 4. Milestone List 5. Approved Change Request |
1. Preamble Diagram method 2. Arrow Line Diagram method 3. Schedule Network Template 4. Determine the dependency relationship 5. Advance, lag |
1. Project Plan Network Diagram 2. List of project activities 3. Activity List Properties 4. Changes initiated |
3. Estimated activity Resources |
Input |
Tools and Technology |
Output |
1, Enterprise environmental factors 2. Organizational Process assets 3. List of activities 4. Activity Properties 5. Availability of resources 6. Project Management Plan |
⑴ Expert Judgment method ⑵ Replacement Scenario Determination ⑶ Public estimate data ⑷ Estimating Software ⑸ Bottom-up estimation |
1. Activity Resource requirements 2. Updated Activity Properties 3. Resource breakdown structure (RBS) 4. Updated resource calendar 5. Change Request |
4. Activity duration estimate. |
Input |
Tools and Technology |
Output |
1, enterprise environmental factors, 2, the organization of the process assets, 3, the scope of the project description, 4, the list of activities, 5, Activity list properties, 6, activity resource requirements, 7, resource calendar, 8, project management plan; |
1. Expert Judgment 2. Analogy Estimation method 3. Parametric estimation 4, the duration of three points estimate 5. Reserved time |
⑴ Activity Duration Estimation results ⑵ Activity list, properties (update) |
5. Making progress Plans |
Input |
Tools and Technology |
Output |
1, the organization of the process assets, 2, the scope of the project description, 3, Activity list, activity attributes, 4, Project Schedule Network Diagram, 5, activity resource requirements, 6, resource calendar, 7, Activity duration estimate, 8, project management plan |
1, Progress network analysis, 2, Critical path method, 3, progress compression, 4, hypothetical scenario analysis, 5, resource balance, 6, key chain, 7, project management software, 8, calendar used, 9, lead and lag, 10, speed model; |
1, Project schedule (Progress Network Diagram, Gantt Chart, milestone map), 2, speed model data, 3, progress benchmark, 4, resource requirement update, 5, activity attribute update, 6, project calendar update, 7, request change, 8, project management plan update; |
6. Progress Control |
Input |
Tools and Technology |
Output |
1. Project Schedule 2. Progress Benchmark 3. Performance report 4. Approved Change requirements |
1, progress report, 2, Progress Update control system, 3, performance measurement, 4, project management software, 5, deviation analysis, 6, plan comparison Gantt chart; |
1, speed model data update, 2, Progress benchmark update, 3, performance measurement, 4, change demand, 5, proposed corrective action, 6, organizational process assets, 7, Activity list, attributes, 7, project management plan; |