If the project is successfully closed and transferred to another department in the company, and the project resources become part of the company's functional organization, the termination type is?
A abort
B add
C package
D outsourcing
Analysis: This is an obvious super-Outline question. Not only does PMBOK contain this knowledge point, but it is not mentioned in most project management books. Fortunately, I explained this knowledge point in detail in the first book, project management-new management perspective, version 4th (e-Industry Press.
When talking about project termination (including normal termination), the book says there are four types of termination:
1. Absolute termination: The project is completed and the team is disbanded.
2. Additional termination: after the project is completed, the entire project result and project team will become independent subsidiaries and the subsidiary will be operated under the parent company.
3. Integrated termination: after the project is completed, the project result and project team become a functional department and operation of the company.
Iv. Self-destruction termination: if the project is not completed, it is abandoned and left to survive.
The four ABCD options in this question are different from the above four, which may be a translation problem. At that time, I did not pay attention to the English expression of the test. I intuitively thought that if the test was terminated by the above four methods, the, B, and C options correspond to the first, second, and third termination methods respectively.
The situation described in this topic is similar to that described in the third part: Integration termination. Therefore, I suggest C.