In order to write a book, I found a project with only seven days after reviewing my emails over the past few years. From the project daily report, I felt that the days of hard work were just like yesterday:
2009
Year
3
Month
23
On Monday, I received a task to help
3
Month
31
A project will be created at the press conference next Tuesday. I have done a lot of such fire-fighting tasks. At the beginning, my boss always opens my mouth
O
-How is this possible? but at the end, we made the boss's mouth open repeatedly.
O
Type -- actually did it!
Early in the morning, I received a task and quickly found someone to build a temporary team, develop a time plan, and discuss the project plan ...... I have always been opposed to working overtime, but in this case, it is inevitable to leave late at night. However, I
There is still room for the plan: to prepare for the launch on Friday, do not work overtime on weekends as much as possible, and move around next Monday. Let's take a look at the email to see the current situation.
Topic: nth
1/7
Day, cube plan
2.0
, Project progress report:
Sending time:
2009
Year
3
Month
23
Day
Hi all, the project has only seven working days in total. Everything is simplified and try the free-body daily report.
The main progress is as follows:
1. Kick off is finished;
2. determine the scope and solution of the project;
A)
Extract and analyze data, and confirm the Project Plan (see the attachment for details );
B)
A function is free and the maximum number of accounts is canceled;
C)
Rubik's Cube 1.0 legacy issues join the project: Update help, modify "Newbie", and replace home page ads and links;
D)
TK .) Relevant Questions start from another project. We will only notify users before January 1, March 31.
3. Demand writing;
A)
The PRD is attached for review tomorrow morning.
4. Team formation;
A)
Developers (XX and XX) moved to the 8th floor to work in a centralized manner;
B)
The test resource will be confirmed after the requirement review is completed tomorrow.
5. Notify stakeholders.
A)
XX Search Engine
: Xx
;
B)
Product: XX and XX.
Important announcements for tomorrow:
1. Demand review;
2. Go to design and development.
Topic: nth
2/7
Day, cube plan
2.0
, Project progress report:
Sending time:
2009
Year
3
Month
24
Day
22: 44
Hi all, today is the 1st day of the project,
Thank you for your support during the evening. The progress is as follows:
1. Requirements review and confirmation are completed in the morning;
A)
Demand is frozen at work. For the final draft, see the attachment.
2. Enter the development stage in the afternoon;
A)
Only 16 working hours, submit the test at noon on Thursday;
B)
TC review tomorrow afternoon.
3. determined by the tester;
A)
So-and-a-half-so may need to work overtime over the weekend;
B)
There is a risk of insufficient personnel, which can be monitored at any time. The monitoring sites are Friday and Sunday.
4. Follow up related matters.
A)
Financial personnel follow up and modify the User Agreement;
B)
Service personnel modify help;
C)
Plan formulation;
D)
Follow up on training matters;
E)
Work with operations to sort out MF and TK materials.
Topic: nth
3/7
Day, cube plan
2.0
, Project progress report:
Sending time:
2009
Year
3
Month
25
Day
20: 19
Hi all, today is the 1st day of the project. The progress is as follows:
1. Development;
A)
In the evening, some features are submitted for testing half a day in advance. Thank you for your efforts.
2. TC review;
A)
The six testers checked and thanked everyone for their support.
3. Follow up related matters.
A)
Financial Personnel modify the User Agreement and submit it before leaving work on Friday;
B)
Service personnel modify help;
C)
Formulate a plan and confirm the principles;
D)
Work with the operations to sort out MF and TK materials, and a certain person is responsible for making pages;
E)
Follow up on training matters.
Topic: nth
4/7
Day, cube plan
2.0
, Project progress report:
Sending time:
2009
Year
3
Month
26
Day
19: 52
Hi all, today is the 1st day of the project. The progress is as follows:
1. Development:
A)
All tests are submitted. According to the test personnel, the quality is good. Thank you;
2. test:
A)
By the end of work, it was about 1/3 working days ahead of the plan;
At present, everything is smooth, but the project has been over half the time, so we are not allowed to lose anything. + u ~~~
Topic: nth
5/7
Day, cube plan
2.0
, Project progress report:
Sending time:
2009
Year
3
Month
27
Day
Hi all, today is the fifth day of the project. The progress is as follows:
1.
The first round of testing is completed, bug
All modifications have been completed. Wait for the next Tuesday to cooperate with the press conference.
2.
During the weekend test, the students will work overtime to test again, and other personnel will be on standby.
3.
The team will be temporarily disbanded for one day next Monday and will be released next Tuesday. Thank you.
There were no major problems in the next weekend. The sixth sky came out, and the seventh day of the release was also very smooth. This is my favorite style, so it's so cool, but how many times can it be so lucky.
Iamsujie:
- Product Design Experience (3012) how to implement the "Boss project" (9)
- Product Design Experience (3015) some bugs in the project (8)
- Product Design Experience (3014) process items of agile practices (2)