The estimated cost isComplete Project ActivitiesThe process of approximate estimation of required funds. Cost prediction made based on known information at a specific time point.
Rough Rom estimation of the number of items available in the startup phase
Input:
- Scope reference: Scope statement, work breakdown structure, and work breakdown structure dictionary.
- Project progress plan
- Human resources plan
- Risk Register
- Business environment factors: market conditions, published commercial databases
- Assets in the organizational process: Cost Estimation policies, cost estimation templates, historical information and lessons learned
Tools and technologies
- Expert judgment
- Analogy estimation: the parameters and indicators of the current project are estimated based on the parameter values and scale indicators of similar projects in the past.
- Parameter Estimation: statistical relationship between historical data and other variables is used. Accuracy depends onParameter ModelMaturity andBasic DataReliability
- Bottom-up Estimation
- Three-point estimation: PERT (the most likely cost is cm, the most optimistic cost is CO and the most pessimistic cost is CP) Ce = [Co + 4 Cm + CP]/6
- Reserve Analysis
- Quality Cost
- Project management estimation Software
- Seller bidding Analysis
Output
- Activity Cost Estimation: quantitative estimation of the costs that may be required to complete the project
- Estimation Basis
- Project File (update)