"Daily scrum" first day 7-magic Sprint1 plan meeting Results
--Group members: Tri Le Huangxiaofei tang di Zhao Yuxuan
The Sprint planning meeting is critical and should be considered the most important activity in Scrum. If it does not perform well, the entire sprint will even be destroyed.
The Sprint planning meeting is also designed to allow the team to get enough information to work undisturbed for a few weeks and to give the product owner full confidence.
In order for our products to be born smoothly, our group conducted a SPRINT1 program, primarily to set Sprint goals and backlog of products based on previously evaluated results.
Sprint Planning Session 1: set sprint goals and established product backlog.
meeting time: 4.15. Eight o'clock in the evening
Meeting Venue: learn a cafeteria on the second floor
Conference Process
•First of all, our teamsprint General introduction to the goals, Tangram backlog.
Then we estimated the time spent on the SPRINT1 plan and Split backlog entry. Clarify the meaning of each entry. The importance level is divided according to the functionality of each entry.
· after we chose to put sprint1 Finally we are scrum meeting schedule fixed time and place. and written as a task card, each person carries out pair programming and task picking.
Outcome of the meeting: 7-magic Backlog
The backlog includes the following:
•ID (serial number)--The uniform identifier is a self-growing number. Prevent them from being found after renaming the story.
•Name(name)--a short, descriptive story name.
•importance initial estimate (initial estimate)--our preliminary estimate, Represents the amount of work that is required to complete the story compared to other stories. The smallest unit is the story point (story pointman-day". &NBSP,
how to demo (how to do the presentation)--it roughly describes how the story should be sprint notes
There's a picture of the Truth O (∩_∩) o~
Determine the total amount of work, divided into the following three parts, because the front desk is the façade, is the basic idea, so the discussion of the front desk by our four small partners to cooperate. Follow-up will continue to develop backstage, link database.
Division of Personnel:
PS: Because forget to buy convenient paste, only A4 paper will (⊙o⊙) Ah! Must be improved next time
Id |
Names (name) |
Importance (IMP) |
Initial estimate (EST) |
Annotations (NOTE) |
Claiming person |
1 |
interface one: First interface |
8 |
4 days |
① " Enter the game " ②" Settings "   |
Don Dee |
2 |
interface two: level |
8 |
4 days |
show, List all levels |
Huangxiaofei |
3 |
interface three: main interface |
10 |
4 days |
< Span style= "font-size:15px;" >① workspace ② example picture |
< Span style= "font-size:15px;" > Tri Le |
4 |
interface four |
8 |
4 day |
① ② share |
Zhao Yuxuan |
5 |
meeting record |
10 |
daily |
① record three words per person ② determine when and where to stand the meeting |
Don Dee Zhao Yuxuan |
6 |
blog Edit and publish |
10 |
daily |
edit meeting minutes and project progress Summary |
Don Dee |
7 |
Interface adjustment and beautification |
9 |
Every day |
Elegant interface, user interaction is strong. |
Zhao Yuxuan |
Picture:
Time and place of next meeting:
4.19 study a canteen second floor, when the moon is black and high.