Soft Test Information System Supervisor: April 29, 2016 homework

Source: Internet
Author: User

First, information application system analysis design stage supervision
1. What are the entry conditions for demand analysis? Remember
1) The owner's unit and the contractor are signing the construction contract, and the preliminary

Project development plan to reach a consensus, you can enter the requirements analysis phase.

2. What is the objective of the demand analysis?
Describe the function and performance of software, determine the constraints of software design and soft

Interface details with other system elements to define the other validity of the software

Demand.

3. What are the results of the demand analysis phase? Remember
1) project development plan;
2) software Requirement specification;
3) Software Quality Assurance program;
4) software configuration management plan;
5) Software (Preliminary) validation test plan;
6) First draft of user's instruction manual.

4. What are the entry conditions for the software outline design phase? (Remember, and understand

: Add no outline 2 words, the answer is the same)
1) project development Plan, quality assurance plan, configuration management plan and other supporting

The plan passes the appraisal and the formal approval;
2) software Requirements specification through review;
3) configuration Management distribution baseline based on the software Requirement specification as the core

State

5. What are the entry conditions for the detailed design phase of the software?
1) Software Summary design description through the review;
2) software outline design description, external interface design has been included in the configuration management by

Control Library.

6, the description algorithm in addition to the flowchart, there are some other tools, such as which 3

Two
1) Pad diagram, problem analysis diagram, problem analyzing diagram;
2) PDL language (pseudo code), Procedure Design Language,

Can be called pseudo-code or structured language;
3) HiPo chart, hierarchy plus input-process-output.

7. What are the results of the software design phase? Remember
1) Summary design specification;
2) database design Manual;
3) User manual;
4) Software Summary Design Manual (Database design section can be a single book)


5) detailed software design instructions;
6) software Coding specification;
7) Integrated test plan.

8, software engineering requirements of software quality assurance as the core, tightly grasp which

8 main links?
Software production methods, requirements analysis, software design, software tools,

testing, verification and validation, review and management.

Second, information application system implementation stage supervision
1. What is the entry condition for the coding phase? Remember
1) software Detailed design instructions have passed the review;
2) software Detailed design instructions have been entered into the configuration management controlled library.

2. Unit test entry conditions?
1) complete all unit codes;
2) Software unit error-free through the compilation;
3) Complete static testing such as code review;
4) All software units are incorporated into the Software Development Unit's configuration management managed library.

3, integration test entry conditions?
1) The Integrated Software Unit is error-free through compilation;
2) The Integrated Software Unit is reviewed by code;
3) The Integrated Software Unit is tested and tested to meet the test requirements by the Unit


4) The Integrated Software Unit has been placed in the Software Development Unit's configuration management by

Control Library;
5) software assembly testing and testing tools with integrated test plan requirements

With.

4. Confirm the test entry conditions?
1) The software completed the integration test;
2) software can be run;
3) All software problem reports and software modification report forms;
4) The entire source program, which is consistent with the Software Modification Report form, has been modified

Code.

5, the system test access conditions?
1) Complete and pass the software verification test;
2) All software products are under the Configuration management control;
3) already has the software system test environment.

6, the focus of the commissioning phase of supervision? Remember
1) to assist the owners and the contractor to deal with the system during the trial run

Issues, and record them;
2) for some recurring problems, in the acceptance test to give the necessary

Concern and supervise the necessary measures of the contractor;
3) supervise and inspect the training work of the contractor's trial operation stage.

7, the focus of technical training supervision? Remember
1) supervise the contractor to formulate the training plan according to the contract and the owner's request;
2) to review the operability of the training plan;
3) require the training program to define the target, training materials, training

Training methods and training of teachers;
4) supervise the implementation of the technical training program and evaluate the training materials and teachers

To inform the owners of the implementation and effectiveness of the training plan.

Supervision of the acceptance stage of information application system
1. What are the prerequisites for the acceptance of the information application system? Remember
1) has passed the computer software validation test review;
2) has passed the System test review;
3) All kinds of documents stipulated in the contract or the appendix are complete;
4) software products have been placed under management;
5) Other acceptance conditions stipulated in the contract or the annex to the contract.

2. What are the working steps for acceptance? Remember
1) Submit the acceptance application;
2) make the acceptance plan;
3) Establishment of the Acceptance Committee;
4) Carry out acceptance test and configuration audit;
5) Conduct acceptance review;
6) Form the acceptance report;
7) Transfer of products.

3, the information application system acceptance can be divided into which 2 large parts? Their order

What kind of work can be divided into?
Software configuration audit and acceptance testing;
The approximate order can be divided into: Document audit, source code review, configuration script

Audit, test program, or script audit and executable program testing.

4. What are the main development documents?
Requirement Specification, summary design instruction, detailed design specification, data

Library design manuals, test plans, test reports, program maintenance manuals,

Programmer development Manuals, user manuals, and project summary reports.

5. What are the main management documents?
Project proposal, quality control plan, configuration management plan, user training

Plan, Quality summary report, review report, meeting record and development progress

Monthly.

6. What are the prerequisites for acceptance testing? (i.e., before the user acceptance test

What work has been done in general? )
1) software development has been completed, and all resolved the known software defects;
2) Acceptance test plan has been reviewed and annotated and placed in document control

Under
3) The review of the software requirements specification has been completed;
4) The review of the summary design and detailed design has been completed;
5) Review of Unit, integration, system test plans and reports has been completed


6) Review of Unit, integration, system test plans and reports has been completed


7) All test scripts have been completed and executed at least once, and

Review
8) Use the Configuration management tool and the code is placed under configuration control;
9) The Software problem processing process is ready;
10) has developed, reviewed and approved the acceptance test completion standards.

7. How to deal with the failure of acceptance?
The contractor shall revise the relevant questions as soon as possible according to the acceptance assessment and

Carry out acceptance or transfer to the contract dispute processing procedure.

8. What are the supervisory measures for system handover?
1) Review the list of project information of the contractor;
2) Assist the owner and the contractor to transfer the project information;
3) Ensure the consistency of software documentation and software;
4) Development software to backup, storage in a safe place, file material archiving

9. What are the supervision measures of the system guarantee period?
1) Supervision of the contractor according to the "contract" provisions of the timely system protection, pumping

The implementation of the system safeguards;
2) to record the quality issues raised by the project owner;
3) supervise the contractor to repair and maintain the unit;
4) Confirm the contents of the repair by the contractor.

Soft Test Information System Supervisor: April 29, 2016 homework

Contact Us

The content source of this page is from Internet, which doesn't represent Alibaba Cloud's opinion; products and services mentioned on that page don't have any relationship with Alibaba Cloud. If the content of the page makes you feel confusing, please write us an email, we will handle the problem within 5 days after receiving your email.

If you find any instances of plagiarism from the community, please send an email to: info-contact@alibabacloud.com and provide relevant evidence. A staff member will contact you within 5 working days.

A Free Trial That Lets You Build Big!

Start building with 50+ products and up to 12 months usage for Elastic Compute Service

  • Sales Support

    1 on 1 presale consultation

  • After-Sales Support

    24/7 Technical Support 6 Free Tickets per Quarter Faster Response

  • Alibaba Cloud offers highly flexible support services tailored to meet your exact needs.