Many friends use Microsoft Project in their work. As a veteran project management software, Microsoft Project features are more robust, especially with Microsoft's SharePoint servers.
Sometimes, though, we may rarely use Microsoft Project fully, after all, she still has a lot of people do not conform to the use of habits, project management methods, maybe we use her to draw a bar chart (Gantt Chart) more time! There's nothing wrong with that, Everyone has their own habit of using the software, but it's a bit of a "overkill" in Microsoft Project if it's just a bar chart for making progress plans!
In fact, from Microsoft Project, still can make beautiful progress Plan bar chart!
There are a lot of tutorials about using spreadsheet software to make Gantt charts in Microsoft Excel, and there are plenty of ready-made templates to download, but most of the templates are made by foreigners, and personal feelings are quite different from our domestic practices.
Below I introduce a simple way to do a bar chart, with the software is very common software-jinshan WPS spreadsheet software, you can go to Jinshan WPS official website for free download, use. I introduced this method is to use Jinshan WPS chart function of the "Stacked bar chart" to achieve, is roughly the following steps.
1, input data create a new form file, in three columns in turn, enter the work content, start time, duration, roughly the following figure.
2. Insert Stacked bar chart to open the Insert menu, select Insert Chart, and select Stacked bar in chart type.
When selected, click Next. In the Source Data window, select the data to produce in columns, click the button in the red box below, and select the three columns of data that you entered earlier.
Triple Recommendation: Click for free Download the latest version of WPS Office software "to see more computer tutorials
Turn off the "Source data" window, and the "Source data" window appears in the image below.