1. Activity
2. Activity Definition
3. activity description/description, AD = activity description
4. Estimation of Activity Duration, Activity Duration estimating
5. Arrow Line Network Diagram (dual-code network diagram), AoA = activity-on-Arrow
6. node network diagram (single-code network diagram), Aon = activity-on-node
7. Actual cost of executed work, acwp = actual cost of work completed MED
8. actual completion date, AF = actual finish date
9. Actual start date, as = actual start date
10. Administrative ending: administrative closure
11. arrow lines and Arrow
12. arrow line display method, ADM = arrow diagramming method
13. Backward pass
14. Horizontal chart and bar chart
15. Baseline plan
16. Completion Budget, BAC = Budget at completion
17. budget estimate, budget estimate
18. Budgeted cost, bcwp = budgeted cost of work completed MED
19. planned execution budget, bcws = budgeted cost of scheduled
20. Calendar Unit
21. Change Control Board, CCB = Chang Control Board
22. Communication and planning
23. Parallel engineering, concurrent engineering
24. Unexpected charges, contingencies
25. Unexpected reserve, Contingency allowance
26. Unexpected planning and Contingency Planning
27. Unexpected reserves, contingency reserve
28. Contract, contract
29. contract management, contract administration
30. Contract close, contract close-out
31. Control
32. Control Chart
33. corrective action, corrective action
34. cost budget, Cost Budgeting
35. Cost Control and Cost Control
36. cost calculation, cost estimating
37. quality cost, cost of quality
38. Cost Performance Index, CPI = Cost Performance Index
39. Cost deviation, CV = Cost Variance
40. work now, crashing
41. Key Processes and critical activities
42. Key route, critical path
43. Key Route Method, cpm = Critical Path Method
44. Current completion date, current Finish Date
45. Current start date
46. Data Date, DD = Data Date
47. deliverables, deliverable
48. Dependency and dependency
49. Virtual activity, dummy activity
50. Duration, du = duration
51. Duration compression, duration Compression
52. earliest completion date, EF = early finish date
53. Earliest start date, ES = Early Start Date
54. Earned Value Method, ev = Earned Value
55. Earned Value Analysis, Earned Value Analysis
56. Labor volume, effort
57. estimation, budget estimate, estimate
58. estimate the cost at completion. EAC = estimate at completion
59. estimation at completion, etc = estimate to complete
60. Single-node event diagram, event-on-node
61. exception report
62. completion date, finish date
63. When the link is completed, FF = finish-to-finish
64. After the link is completed, FS = finish-to-start
65. Time Difference, maneuver time, floating time, float
66. forward calculation method, forward pass
67. Free time difference, FF = free float
68. Functional manager and functional Manager
69. functional organization, functional organization
70. Gantt chart and Gantt Chart
71. Graphic review technology, Gert = graphical evaluation and review Technique
72. Work together, Hammock
73. Hanging pendulum, hanger
74. Information Distribution and information distribution
75. Project Initiation
76. Comprehensive Cost/Progress Report, integrated cost/schedule reporting
77. Invitation, IFB = invitation for bid
78. Key Event Schedule
79. latency, lag
80. Latest completion date, LF = Late finish date
81. Latest start date, ls = Late start date
82. Advance workload, lead
83. End-to-end cost estimation, life-cycle costing
84. Product Manager, line manager
85. Logic Diagram
86. Logical Relationship, logical relationship
87. Loop and loop
88. Manage reserves and manage reserve
89. Master Schedule, Master Schedule
90. matrix organization, matrix organization
91. milestone, milestone
92. Milestone schedule, milestone schedule
93. modern project management, mpm = modern project management
94. Monitoring and monitoring
95. Monte Carlo analysis, Monte Carlo Analysis
96. Key tasks, near-critical activity
97. Network
98. Network Analysis
99. network logic
100. network route, network path
101. Node
102. Organization Breakdown Structure, obs = organizational Breakdown Structure
103 organizational planning, organizational planning
104 overall change control, overall change control
105. overlap, overlap
106 parameter estimation method, parametric estimating
107, line, path
108. Line Time Difference, path float
109. Completion percentage, Pc = percent complete
110 execution report, performance reporting
111. Implementing organization, discovery Organization
112 plan review technical diagram, PERT chart
113 planned completion date, pF = planned Finish Date
114. planned start date, PS = planned start date
115 priority graph method, PDM = precedence diagramming method
116 priority, precedence relationship
117 pre-work, predecessor Activity
118 procurement planning and procurement planning
119 Project, Program
120 Plan Review Technology, pert = program evaluation and review Technique
121. Project
122 Project License, project charter
123. Project Communication Management
124. project cost management and project cost management
125 Project Human Resource Management
126 integrated project management and project Integration Management
127 project life cycle
128. Project Management, PM = Project Management
129 project management knowledge system, PMBOK = project management body of knowledge
130. Project Management Software
131 Project Management Team
132 Project Manager, PM = Project Manager
133 Project Network Diagram, Project Network digoal
134 project phase, Project Phase
135. Project Plan
136. Project Plan Development
137 project plan execution
138. project planning, project planning
139 project procurement management, project procurement management
140. Project Quality Management
141. Project Risk Management
142 project schedule, Project Schedule
143. Project Scope Management
144. Project team member, project team member
145. Project Time Management
146 project organization
147. Quality assurance, QA = Quality Assurance
148. Quality control, qc = Quality Control
149 quality planning, quality planning
150 remaining duration, rdu = remaining duration
151 request proposal, RFP = Request for Proposal
152 request quotation, RFQ = request for quotation
153. Reserves, reserve
154 resource balance, Resource Leveling
155 resource constraint schedule, resource-limited schedule
156. Resource Planning
157 Responsibility Assignment Matrix, Ram = Responsibility Assignment Matrix
158 responsibility chart, responsibility chart
159 responsibility matrix, responsibility matrix
160 reserve gold, retain age
161 emergency, risk event
162 risk identification, risk identification
163 risk response control, risk response control
164 risk response development, risk response development
165. S curve, S-curve
166. Schedule, schedule
167 Schedule Analysis, Schedule Analysis
168. Schedule Compression, Schedule Compression
169. Schedule Control and Schedule Control
170 progress execution index, SPI = schedule performance index
171. Progress deviation, SV = schedule variance
172 planned completion date, Sf = scheduled Finish Date
173. planned start date, Ss = Scheduled Start Date
174. Scope
175 scope benchmark plan, scope baseline
176 Scope change
177 Scope change control
178 scope definition
179. Scope Planning
180. Scope Verification
181, time difference, slack
182. Inquiry, solicitation
183 inquiry planning, solicitation
184 recruitment of staff, staff acquisition
185. project stakeholders, stakeholder
186 start date
187. start-to-finish
188. start-to-start
189 work instruction, sow = Statement of Work
190. subnet, Subnet
191 subnetwork, subnet work
192. Follow-up work, successor Activity
193 target completion date, Tc = target completion date
194 target time plan, target schedule
195. Task
196 team building and team development
197. Team members, team members
198 time-scale network diagram, time-scaled network digoal
199 target completion date, TF = target Finish Date
200 target start date, TS = target start date
201. Total time difference, TF = total float
202. Total Quality Management, TQM = Total Quality Management
203. contingency measures, workaround
204. work breakdown structure, WBS = work breakdown structure
205. Work Package