In the practice of agile development, it is a necessary practice to realize team collaboration and transparent management through visual task Kanban. By visualizing the task Kanban we can achieve several purposes:1. Visualize the objectives of the management team;2. Define the priority of the target;3. Clarify the task items after the target decomposition;4. Visualize the progress of management tasks.Agile
front of the board in turn to speak, stand in the chair, find your responsible task, tell everyone three things 1, yesterday did what 2, what plan today 3, I have any difficulties or needs what assistance. While speaking, adjust the status of the note to ensure that the team is aware of the progress of the project. The team leader summarizes and reports the overall goals of the group and the problems that need to be solved.
When the note needs clarification and design clarification, team leade
This case describes how to use Kanban and lean development techniques to save a "red" project.
Background
This article is about a large client user development project that has been around for almost a year. Backwards and forwards, the development team maintained a base of 10 to 15 members.
At the beginning of the project, the team used the traditional waterfall development model. Before the code development phase is the requirements analysis phase
Kanban View is probably the most flexible view in Odoo. It can be used for many different purposes. One of the most common ones is splitting items to distinct groups (represented by a row of columns) and allowing users T o Drag items between those groups. For example thehr_reqruitmentmodule lets users to manage applications the this.It ' s trivial and well documented how to group objects in Kanban. Just Add
Signature
In the 21st century, the most important job of enterprise managers is to improve the productivity of internal knowledge workers, so that knowledge workers can manage themselves, learn independently and innovate constantly. People no longer use output to measure productivity, and quality (value) becomes particularly important. Pain points unnecessary deadlines, overly optimistic feature range estimates, make the focus of the work into the work to squeeze the deadline rather than the qua
I've been asked how the lower left corner of the Kanban Niang was added to theJust beginning to see other people's essays look at the face of a confused force, himself a long time to fixSo I wanted to write an essay that was easy to read.1. Download model-related files ( Click on recommendations and follow to download Oh qwq)After you open the package, that's a bunch of stuff.2. Upload the file to the blog parkJust upload
Waifu.css
Waifu-
handled? It does not build solution, but builds all projects in a certain order. Therefore, if Dev adds a project, the script must be changed. -- This script is really not used as a local build script.
VSS. We are a distributed team. The VSS server is located in Shanghai. It takes several hours for foreign teams to obtain code, so they almost don't get it. They only get a solution (not all) that their team is working on every week, and Others copy it from them. The team's code is always outd
The first is to understand and learn the Kanban method of the relevant people, to achieve the goal of using Kanban to reach a consensus.
Let's draw a value stream diagram together.
Identify the environments to be controlled (usually bottlenecks), define work items, and possibly classify them.
Talk to the upstream when you can pull in new work items, talk to the downstream about the conditions for t
corresponding test case completed and passed use case review
In progress-work content
Use case execution
Bug Acceptance (the bug that is generated by the current iteration requirement is closed directly)
Completion-access conditions
Demand-related use cases are running
Demand-related bugs have been fixed
Conditions for acceptance of board listing
The requirement is already in the Test complete column
Job description
Product owner i
iteration. Appropriate reduction of requirements based on the results of the final split.Burndown ChartWhen an iteration is selected, the upper-right corner of the graph is the Burndown chart.Available capacity lines (highest point iteration begins with the maximum working time available, lowest 0)Ideal Trend (maximum value of remaining work at highest point, lowest 0)Remaining Work (line chart for remaining work per day)Use the following resources to learn the Burndown chart:
Https://
One of the conventions in Kanban is that when a work item (task) is blocked, a pink (or red) note is usually attached to the task item. Note the reason for obstruction, date.
The blocked work item should be the main focus of the daily station. The impact may become larger after a period of time. You need to let all members of the team know that there is a situation where the blocked issue is escalated and needs to be known to the person concerned.
Now most teams are talking about agile development, and it seems that agile is a silver bullet for software development. Just need to practice some of the agile development model can be how, in fact, I think whether it is agile development or the traditional waterfall flow development has their market, depending on the composition of the team, depends on the attributes of your products, the market competition environment. The ultimate goal is to achieve the desired requirements in the quickest w
Create | data
How to create a successful data Warehouse (Warehose), the following story will tell you!
The company's ' s ' Warehouse project began with a casual conversation between several executives on their way to LUN Ch. The people involved were the IT manager for decision support as as and as several members of a department that had just Deci Ded to install a data
Linux version number: 14.04.1-ubuntu x86_64
Backup server address is: 172.29.71.59, backup root path is/home/backup
1.git Code warehouse automatic daily backup:
Server address: 172.29.71.111,git specified directory: 00.apps, Backup path is:/home/backup/codeserver_111
Step One:
cd/home/backup/codeserver_111
git clone--mirror Git@172.29.71.111:00.appsgit clone--mirror copies a git library that contains the latest remote branch as well as a history sub
This article outlines the general process of using OWB to create a data warehouse. Oracle's OWB is one of the three most current ETL products. OWB can not only complete data extraction, conversion and loading, but also help users create ROLAP (relational online analysis Process) and MOLAP (multidimensional online) in Oracle database Analysis Process) Data Warehouse objects, data quality management, business
Data warehouse design purpose and data warehouse design purpose
The purpose of data warehouse design or the criteria for measuring success:
1. The data warehouse must make the information of the Organization easy to access.
2. The data warehouse must display information of
WMS is a professional Warehousing Management Software Based on the construction and implementation experience of warehouse logistics management. Compared with traditional inventory management software, it not only includes basic functions such as normal inventory management, such as warehouse receiving and inventory check, but also focuses on the management of warehouse
git modifies the remote warehouse addressThere are three kinds of methods:1. Modify the commandGit remote origin set-url [url]2. Delete First and then addGit remote RM origingit remote add origin [url]3. Modify config file directlygit remote warehouse managementTo participate in the collaboration of any Git project, you must understand how to manage a remote repository. A remote repository is a project
First, what is a data warehouse
The traditional data warehouse concept is that data warehouse is a structured data environment for decision Support System (DSS) and on-line analysis application data source. is a strategic set of all types of data that is supported by the decision making process at all levels of the enterprise.
In simple terms, the previous data
The content source of this page is from Internet, which doesn't represent Alibaba Cloud's opinion;
products and services mentioned on that page don't have any relationship with Alibaba Cloud. If the
content of the page makes you feel confusing, please write us an email, we will handle the problem
within 5 days after receiving your email.
If you find any instances of plagiarism from the community, please send an email to:
info-contact@alibabacloud.com
and provide relevant evidence. A staff member will contact you within 5 working days.