Principles of WBS decomposition:
The principle means that WBS cannot break down items or contain any products or activities out of the scope of the project.
Vertical refers to whether the WBS decomposition should be fine enough to meet the task allocation, detection and control purposes.
With the continuous promotion and widespread acceptance of project management technology, WBS has gradually entered the project manager's vision, one of the core tools for daily project management, it fully embodies the core concept of "decomposition" of PMBOK, which can help the p
The following is the WBS of a widely spread software project on the Internet. I believe many people have created similar WBS.
It is because of our ancestors, the ancestors of the ancestors with similar methods to Create WBS, ears and ears, we also developed the same habit.
This is a typical problematic
disadvantage, because everyone knows that joining a new person in the project will only affect the progress)
In the early stage of the project, as an ordinary employee, what should I do most in this case? I think the most important thing is to make a good personal plan.It is not an overall plan starting from project management, but a personal plan for your own
structure information, cost data, progress data, contract information, product data, and report information.Transfer the work package from the Project Manager AllianceTransferred from project management AllianceA Work Package is the underlying element of WBS. A general work package is the smallest "deliverables ", these deliverables can easily identify the activ
Since there is no WBS, it becomes the core of the project manager to manage the project without project management. Every company with mature project management has a certain WBS template for different types of projects for the
A work breakdown structure (WBS) is the process of progressively dividing project deliverables and project work into smaller, more manageable project units that organize and define the entire project scope. The lowest level elements of a
After thinking about this problem for a while, the conclusion is ridiculous. That is, all the previous WBS reference books are very simple to use due to space limitations. These simple projects can quickly see deliverables and activities, so they are all done at once.
Let's make a comparison. The garage project is based on the deliverables as follows:
The activity-based method is as follows:
T
Work Breakdown Structure
(
Work Breakdown sturcture
):A project element grouping for deliverablesThis group organizes and defines all project work scopes. Each level of descent represents a more detailed definition of project work.
Task
(Task)
: General work content, which is not included in
WBS
But it may
Name:nice! Project name: About run appGroup leader: LiquanMembers: Han Yuanyuan Liu Fangfang Hong Lijun in MiaoBug fixes:1. I see the phenomenon: After exiting the current account, press the Back button to enter the login screen again.Expected phenomenon: safe to log in and exit.The difference between the two: there is no way to safely exit as expected.Bug reason guessing: in Android application there is a stack of data structures stored in the app cl
I. OverviewWBS (wide band speech) popular is Bluetooth broadband call, call data frequency 16K, using MSBC codec (chip in the implementation)Compared with NBS (narrow band speech), NBS is popular in terms of narrowband calls, call data frequency 8K, using CSVD codec (implemented in chip)NBS is the defaultTwo. ImplementTo implement a WBS, it is generally more complexTo be carried out in two phases:1.profile layer (HFP at COMMAND)2.control bluetooth chi
Team Stage Objectives:① Ultimate goal: Develop a mobile app for Android version of the project.② Phase goal: Increase project functionality.③ Initial Goal: Complete the web version of the individual features of the implementation.List of work items:① Homepage Layout design.② feature layout (originally planned only for text and Web pages).③ Text Interface④ URL InterfaceMember Division of work:High-developmen
expenses.Item seven (query interface): Call the calendar to connect to the database for querying.Item eight (total interface): Similar to QQ left and right slide, the main interface and the total interface left and right. Displayed as a percentage of a circle's graph.Iii. details of members work item estimatesChen Chang: project manager, Calendar call, interface jump.Zhang more: Database connection, circle graph percent display.Mao Wenwen: Interface
handheld phones, and by deploying MSBC speech codec systems in Bluetooth headsets . In addition, voice processing algorithms such as noise suppression and echo cancellation in handheld phones and headphones make the HD voice experience even better. As network operators and device manufacturers gradually introduce high-definition voice into the consumer market, the bandwidth scaling approach on Bluetooth headsets can bring the benefits of high-definition voice to narrow-band and mixed-bandwidth
First, the front-end interface: (as of November 20)1, login interface (to be determined, need to specifically discuss whether login function required):Interface design: Wang Guangnan, Zhang Wenjie2, List interface: By default, the classroom is suitable for self-study, arrange all the classrooms and the use of the classroom to allow users to order according to their own needs, such as by the classroom number sorting, the degree of idle sort and so on.Interface design: Wang Guangnan, Zhang WenjieS
Reset when no solution is in place
2
Debug
Bug reports
2
Debug
5
Gantt ChartProperty Description (top to bottom):Art : Draw product logo, draw various button pictures, complete after the program Ape 3Program Ape 3: And program Ape 1, 2 negotiate layout, and implement layout Program Ape 1: Program Ape 1 Complete selection of difficulty algorithm, exit the entire program, discard the current pr
group name: flying daughter policeproject name: Gift Selection Gadgetteam members: Shen Besan (group leader), try, Yang Yuning, Tan Limingcode Address: HTTPS:https://git.coding.net/shenbaishan/gift-selection.gitSSH: [email protected]: Shenbaishan/gift-selection.gitWhat's NEW: guess you like the module
Function
Sub-function
Two-level sub-function
Estimated time spent (hours)
Actual time spent (hours)
Guess you like it.
A low-priced gift
The project budget was carried over through cocj in the R3 system. The result showed that the budget was not found in 0co_om_wbs_8 data source. After some checks, it turns out that notes was not marked, you need to add the relevant bpxx_vtype configuration, use zcosp_vtype_add, zfill_bpxx_vtypeProgramThe execution is OK ..
Ref content:
Https://websmp230.sap-ag.de/sap (bd16aczjptawmq =)/BC/bsp/SPNs/sapnotes/index2.htm? Numm = 0000490233 nlang = 1
H
⑶ Expert Judgment method(4) Project stakeholder analysis
⑴ Project Scope specification (detailed)⑵ Change Request(3) Project management Plan (update)
3. Create a work breakdown structureA work breakdown structure (WBS) is a hierarchical decomposition of project
The content source of this page is from Internet, which doesn't represent Alibaba Cloud's opinion;
products and services mentioned on that page don't have any relationship with Alibaba Cloud. If the
content of the page makes you feel confusing, please write us an email, we will handle the problem
within 5 days after receiving your email.
If you find any instances of plagiarism from the community, please send an email to:
info-contact@alibabacloud.com
and provide relevant evidence. A staff member will contact you within 5 working days.