scrum for dummies

Read about scrum for dummies, The latest news, videos, and discussion topics about scrum for dummies from alibabacloud.com

Scrum Project 7.0

Topic: "How can we do better in the next sprint?"  "Time: 1 hours.  Participants: the entire team.  Location: Dormitory.Clerk: Wu Yuming. 2. Review the Process Sprint Summary: Scrum Master shows you the sprint backlog, with the help of the team, summarizing the sprint, including important events and decisions. At first, the work efficiency is low, and the done value of the Burndown chart is above the ideal value, which is slower than the ideal. Update

"Beta phase" third scrum meeting!

Daily Task content: This meeting is the third Scrum meeting Conference ~ As the meeting project manager is still late (12:30), so in the apartment on the 7 floor, the girls participated in the online meeting, the time for everyone to meet 10 minutes. Players Finish the task yesterday To finish the task tomorrow. Liu Hu #160Completes 1022 of the image processing related work

Scrum Project 2.0

I. Project workRead the 8th chapter of the textbook, 8.1~8.3 section p157~168, learn how to get the user needs, each group can choose one or two to apply.Section 8.4 p168-171 refer to the NABCDA model for specific instructions.Step 1 of the 2.SCRUM processComplete the production backlog and ensure that the product backlog is organized before the Spint planning meeting.Reading the 8th chapter of the textbook, section 8.5 p171~173, helps us prioritize t

[Team Project] Scrum Project 1.0

1. Determine the topic.Use the NABCD model to analyze your initial selected projects and explain the reasons for your selection.Record as a speech video, upload to a video site, and send a link to a team blog.Closing Date: 2016.5.6 10 o'clock in the eveningStep 1 of the 2.SCRUM processComplete the production backlog and ensure that the product backlog is organized before the Spint planning meeting.------------------------------------------------------

Notes of Daily Scrum meeting (11.12)

Today we have the first scrum meeting of the beta phase MOOC project development, which summarizes the alpha phase and then we identifyThe next beta phase of the Project division, and on a daily progress report made a pact, that is, every team member to PM to contact each night, told PM today sinceThe progress of their work, no project progress (such as the newly-transferred students to familiarize themselves with the previous project code) to explain

Scrum Project 3.0

3.0-----------------------------------------------------Steps of the SCRUM process 2:spring plan1. Make sure the product backlog is organized.2. Sprint cycle, a sprint cycle, length of two weeks, this semester also has three sprint cycle.3. Determine the sprint target.3.1 The product owner summarizes the product backlog, provides a general overview of the sprint goals, and tells the story that he considers most important. The 3.2 team discusses each s

"Beta phase" eighth time scrum meeting!

Daily Task content: This meeting is the eighth Scrum meeting Conference ~ As the project manager of the meeting was unwell and did not attend the meeting, the spirit of the meeting was conveyed by the egg, and the other students participated in the meeting. player Yesterday completed the task Tomorrow to complete the task Liu Hu > Today, the bo

Scrum Project 2.0

Read the 8th chapter of the textbook, 8.1~8.3 section p157~168, learn how to get the user needs, each group can choose one or two to apply.Section 8.4 p168-171 refer to the NABCDA model for specific instructions.Step 1 of the 2.SCRUM processComplete the production backlog and ensure that the product backlog is organized before the Spint planning meeting.Reading the 8th chapter of the textbook, section 8.5 p171~173, helps us prioritize the list.8.5 sec

Notes of Daily Scrum meeting (12.16)

Many of the most recent courses have come to the end of the time, a lot of days the players are not out of time to do the project of soft work, so it doesAnd our plan is very big, but I hope the teacher understanding, three curriculum design is really stressful.Today's team tasks are summarized as follows: Team members Team work today Chen Shaojie Learn the parsing of JSON data streams Di Search function Preliminary Code completion

Beta stage Eighth Scrum meeting

Situation Brief Beta stage Eighth Scrum meeting Agile development start time 2016/12/21 00:00 End time for Agile development 2016/12/22 00:00 Summary of basic content of the meeting Deadline near Participate in the discussion staff All participation Length of discussion 2016/12/20 23:00-23:20 20M Specia

Research and Development Management 06:scrum Agile Project Management

This paper summarizes the agile practice process in the actual development process, combining with 5 years of Scrum agile development experience, combined with PMP related knowledge and skills. Starting with the introduction of agile development methodologies, the process of scrum agile development and the application of relevant key skills and frameworks are introduced. Overview: 1. Overview of Agile

Scrum ceremony Sprint planning meeting

meeting time:4.12. Eight o'clock in the eveningVenue: Second School buildingConference Process• First we discussed the experimental first Sprint1 to achieve the function of our initial goal.• We then combed through the tasks and requirements of the first phase.• The tasks are then divided and picked up.• In the end, each person estimates his or her task and makes an appointment for the time and place of the next meeting.team's BacklogInitial total goal: Complete the requirements analysis, to do

Scrum ceremony Sprint planning meeting

· meeting time:4.12 Three o'clock in the afternoonConference Venue: Basic Teaching BuildingConference Process• First we discussed the first Sprint1 of the experiment to achieve the function of our initial goal.• Then further combed through the tasks and requirements of the first phase.• The task is then divided and picked up.• Finally, each person estimates his or her task and determines the time and place of the next meeting.team's BacklogInitial total goal: Complete the requirements analysis,

"Alpha" seventh scrum meeting

Today's mission list: Name Complete the Mission today The time elapsed between Liu Hu There's not much to do today ... Looking at the formatted output of Python 2 Lu Yu Generate a Physical Report experiment pageIssue Link: https://github.com/buaase/Phylab-Web/issues/27 4 Yan Ting Rough version of the personal registration page login, you can make certain judgments 2 Huang Yumeng

Seventh Scrum MEETING-2015/11/1

The new January has begun! Today is the weekend, so everyone's development progress a little slower, enjoy a happy weekend ~Today everyone's development has not encountered any problems, because these days down, we are more familiar with the development process of Android, for the moment will not encounter new problems.Our current project's overall framework has been basically completed, the rest of the main is and the server interaction module, after the sister gave us a new server address, we

"Alpha" eighth scrum meeting

experiencing multiple tribulations, Huang Yumeng completed 1091 of data processing.Issue Link: https://github.com/buaase/Phylab-Web/issues/54 3 Hanwen Mr. Hao today is responsible for processing 1082 of the data, but he went to the waves today, to the meeting did not finish!!! 0!! Harrison He Songo completed 1061 of the experimental data today.Issue Link: https://github.com/buaase/Phylab-Web/issues/47 2 Issn Uncle Li showed

Daily Scrum (2015/10/23)

I did a lot of work this week with my PM. Since this is the day of Friday, some members of the team are going out tonight, and some have been busy for a week to have a rest. So pm and I discuss the task of arranging some readings tonight, giving members some free time to allocate: Members Mission today Time Tomorrow mission Fu Mei Xiao This should be:1. Learn to run the code on the server2. Able to master most of the codeSwitch1. Free reading of

Daily Scrum (2015/10/28)

The dev guys finished a part of the code-style trimming yesterday. Tonight, as we communicate with other groups, we find that our code needs to be run on the server, and the server needs to be configured, and it is said to take some time. So before writing the code PM put forward we should first set up the server, so today everyone's task is to query the relevant information, PM planning a new task. Members Today's mission Time Tomorrow mission Fu Me

Daily standing meetings-agile process scrum practices

in the mutual report and the exchange situation, but does not report to the supervisor or the manager6. The daily meeting should be controlled within 15 minutes7, do not put the daily standing meeting as the beginning of the day, not too early and not too late to avoid someone from the heart of the beginning of the day with this meeting linked.8. The standing meeting shall be held at the same place at the same time every dayNote: The above content is from the network share or summary, for refer

Scrum stand-up meeting

Stand -up meetings are the members of each other who stand up to each other and say their progress, not meetings, not writing reports. is for better communication and coordination, essentially for engineering team communication.The requirements for the scrum stand -up meeting are as follows:1. Members are equal, and statements do not differ between managers and programmers, and everyone needs to keep their statements within 15 minutes.2. The content o

Total Pages: 15 1 .... 11 12 13 14 15 Go to: Go

Contact Us

The content source of this page is from Internet, which doesn't represent Alibaba Cloud's opinion; products and services mentioned on that page don't have any relationship with Alibaba Cloud. If the content of the page makes you feel confusing, please write us an email, we will handle the problem within 5 days after receiving your email.

If you find any instances of plagiarism from the community, please send an email to: info-contact@alibabacloud.com and provide relevant evidence. A staff member will contact you within 5 working days.

A Free Trial That Lets You Build Big!

Start building with 50+ products and up to 12 months usage for Elastic Compute Service

  • Sales Support

    1 on 1 presale consultation

  • After-Sales Support

    24/7 Technical Support 6 Free Tickets per Quarter Faster Response

  • Alibaba Cloud offers highly flexible support services tailored to meet your exact needs.