Basic MRP processing logic

Source: Internet
Author: User

From http://course.cug.edu.cn/cugThird/product_manage/ch7mrp/ch7-2.htm

Location: course learning> Chapter 7> section 2

Section 2,MRPBasic processing logic

I,MRPProcessing logic

MRPThe basic principle is to expand the production schedule of parts from the product delivery date to the demand quantity and demand Date of raw materials and purchased parts, and convert the product production plan to the material demand table, it also provides information for preparing the Capability Requirement Plan.

Its basic processing logic7.2-1.

 

Figure7.2-1 MRPProcessing logic

Slave chart7.2-1Yes,MRPIncluding input,MRPComputing and output:3Parts:

NMain production plan (product production plan,MPs)

NMaterial List (product structure file,BOM)

NInventory Status File

1. MPs

The main production plan mainly specifies the final products to be produced, the time required, and the demand, it is a plan to define the production quantity and production time in each time period according to the product types, models and specifications. It is an external requirement andMRPSystem interface. Table7.2-1OneMPs.

Table7.2-1

 

MPsSome demand data cannot be changed, that is, frozen, such as tables.7.2-2. Generally, the plan to be put into production cannot be changed.

Table7.2-2"Frozen" indicates that changes are not allowed

MPsPlan object:MPsWhat is listed in is what enterprises provide to the outside world. They have the characteristics of independent requirements, including:

UThe final product item is a complete product;

UParts and accessories that are independent of each other can be a complete part or a part.

UMPsThe production quantity specified in is generally the net requirement, that is, the quantity to be produced.

MPsSeveral concepts of time

UPlanning Period: it is also called the planning outlook period and planning level period, which shows how far the main production plan can look. Generally, the planning period should be no shorter than the longest product production period. A longer planning period can improve the foresight of the plan.

UTime period: refersMPsThe time unit. The typical planned period is week or day. The time period length can be set by the user at will. In addition, a long time period can be used in a main production plan. For example, the recent time period is subdivided into days or weeks, and the middle and long ends are months or months.

2.Product Structure Data Maintenance Subsystem

Product Structure Information describes the components of various materials in a product. It describes the varieties of all parts and rough materials in the product, the number of individual parts, and their affiliation. The methods used to describe the product structure include: Product Structure Tree and ticket (Bill of materials,BOM).BOMIt indicates the product composition and structure information, including the list of required parts, the structure level of the product project, and the sequence of each process stage of the final product. Figure7.2-2For bicyclesBOM.

Figure7.2-2BicycleBOM

ExploitationBOMYou can accurately calculate the required information. The materials can be classified into two categories: Self-made projects and procurement projects (including all raw materials, purchased parts and outsourced parts ).MRPAfter the expansion, the material demand plan of the self-made project forms the corresponding production operation plan, and the material demand plan of the procurement project forms the corresponding procurement supply plan.

 

3.Inventory data Maintenance Subsystem

Inventory mainly refers to intermediate inventory of semi-finished products and rough stock.,There are two types of data: fixed data and changed data.

Fixed data, also known as primary data, includes materialCode, Materials, unit price, supply source, supply lead-up period, batch policy, insurance reserves, and inventory type (by capital usage)ABCCategory.

The changed data includes the existing inventory, minimum inventory, maximum inventory, and estimated arrival volume of materials. These data changes frequently over time.

The inventory status file stores data about each item,MRPImportant information about the system, such as what to order, how to order, and when to issue an order, is stored in the inventory status file. The product structure file is relatively stable, while the inventory status file is constantly changing. Table7.2-3Is an inventory status file.

 

 

Parameters of the inventory status file

UTotal requirement: determined by the planned order quantity of the Upper-layer components.

UExpected Delivery volume: the number of projects in a future period. It comes from the Procurement Order or production order in progress.

UExisting quantity (existing inventory): the current inventory of the corresponding time, which is the actual available inventory of the warehouse.

UQuantity allocated: The quantity of materials that have been allocated to a user but have not been taken from the warehouse.

UNet demand: when the current number and estimated arrival volume cannot meet the total demand, a net demand will be generated.

UPlanned order quantity: Number of materials that must be put into production to ensure the demand for parts. Plan to issue orders should consider both the early stage and the safety inventory, batch rules and loss.

Inventory status data can be divided into two types: inventory data and demand data. The expected arrival volume, allocated volume, and existing quantity of inventory data must be checked before entering the system. The total requirement, net requirement, and planned delivery volume are the required data, which is calculated by the system.

 

4. MRPProcessing Process

UPreparationMRPProcess the required inputMPsDelivered as a confirmed production orderMRP.

UBased on the product'sBOMFrom the first layer of the project, process each project layer by layer until the minimum layer of the Project is processed.

 

 

5Planned Order QuantityPi(T) : The ordering task assigned to the production department or the procurement department. Generally, the net requirement is the planned order quantity, but the actual order quantity should be considered.

6And planned input volume. It refers to the quantity invested in production or proposed procurement. In terms of quantity, it is generally equal to the planned order quantity. It only pushes the time from the delivery time of the order amount to an early stage.L.

Iii. Batch Adjustment

Determine the basic assumptions of batch Based on relevance requirements:

(1) The demand for materials within each period of the planned period is known and must be met;

(2) The order quantity can and can only cover one or several cycles of demand. You cannot separate the demand for one cycle and then separate it into several batches;

(3) To meet the current needs of the batch direct to the user, not into the inventory, so there is no storage costs.

Common batch rules

(1) The fixed order quantity method specifies a fixed order quantity. Each time you need to place orders in batches, the batch is determined based on experience and related conditions. If the net demand is less than the batch, the order is made in batches. If the net demand is greater than the batch, the order is made in the net demand.

(2. The net requirement is directly used as the order quantity.

(3) Fixed order interval. Pre-set a fixed order interval, and then combine the demand in this interval into a batch order, the arrival time is in the first week. The selection of the interval is often in line with the interval of the preparation plan of the enterprise, and the value of materials should be taken into account.

 

IV,MRPBasic processing logic

Layer by product structure, from top to bottom. For each layer, determine the total demand, and then calculate the net demand based on the number of products in process and Inventory (if necessary, adjust the net demand to the planned order quantity in batches ), calculate the total demand for sub-item materials based on the net demand and product bill,7.2-3.

example: the factory producing wooden blinds receives two blinds orders: one copy 100 , 150 . 100 units should be shipped in the fourth week, 150 orders in units are delivered at the beginning of week 8. Each shutter includes 4 wooden parts and 2 frames. The wooden part is made by the factory. The production process is time consuming 1 weekly, the framework must be ordered, the order start time is 2 Week. It takes 1 weeks to assemble the blinds. 1 70 . Solve the order scale and time.

Requirements:1By direct batch

2Batch order is320Organization Framework and70Unit: wooden part

 

 

5. Update the material demand plan

1, Regenerate the update Method

It mainly targets situations where production conditions are stable and the plan changes little. It is generally a regular update. During the update, the item is recalculated layer by layer starting from the zero layer.

2Net change update Method

It mainly targets unstable production conditions and large planned changes. Only plans for re-computing and updating those changed projects.

Contact Us

The content source of this page is from Internet, which doesn't represent Alibaba Cloud's opinion; products and services mentioned on that page don't have any relationship with Alibaba Cloud. If the content of the page makes you feel confusing, please write us an email, we will handle the problem within 5 days after receiving your email.

If you find any instances of plagiarism from the community, please send an email to: info-contact@alibabacloud.com and provide relevant evidence. A staff member will contact you within 5 working days.

A Free Trial That Lets You Build Big!

Start building with 50+ products and up to 12 months usage for Elastic Compute Service

  • Sales Support

    1 on 1 presale consultation

  • After-Sales Support

    24/7 Technical Support 6 Free Tickets per Quarter Faster Response

  • Alibaba Cloud offers highly flexible support services tailored to meet your exact needs.