Recently in the document, because the master acceptance of the document should have some of the pictures are not joined, so owe after all to change back, but there is also a benefit is that there is reason to know something more, maybe if the project leader in the future or do not have this task assigned to me will never touch.
Here's a look at the Gantt Chart in our project development plan document:
1. Write your task, start time, duration, Finish time in Excel
2. Check the contents of the table--insert--Small arrow
3. An interface with the Insert icon--all icons--bar chart--the third can be
That appears as:
4. Double-click the project is located in the vertical, early summer you set the axis format, select reverse category
5. Select the icon and right click on "Select Data"
6. Delete the finish time, keep the start time and duration, and make sure that the start time is on, the duration is below
That appears as:
7. Click "Start Time" to select No fill, no border
8. The graphic is basically complete, then design the "time" format, right-click on the title time--Set the axis format
Write minimum in boundary: 2016-1-25 Max: 2016-3-20, and then we'll find it automatically becomes the number of its system, but we don't have to bother
So the Gantt chart was created successfully!
Version Excel2013--Gantt chart