How to lead a project

Source: Internet
Author: User

Hello everyone:

I haven't come up for a long time. Today, the leader has given a work plan for the 2010 fiscal year, and the overall feeling is okay. I am responsible for this. Let's not talk about it. Please help me out your mind.

Next this year, I will be responsible for the "Asynchronous processing and parallel computing" of the company's products, making full use of the performance improvements and good user experience brought by asynchronous processing and parallel computing, the GSP framework of the company's products is capable of asynchronous processing and parallel computing. So next, I want to focus on it.Asynchronous processing and parallel computingThis task is finished.

1. Current resources:

The 1.1 company assigned two people, technically not to mention, but it was longer than me, a development manager and an experienced Development colleague.

1.2 it is necessary to work closely with the message platform in the product and the task planning function, and develop at the same time.

1.3 The leaders granted me the authority of the person in charge. I can control many resources, meetings, and task arrangements on my own.

2. What I want to achieve:

2.1 complete the task on time, by quality, and smoothly.

2.2 make highlights and satisfy the market, company and leadership.

2.3 Add a bright performance to yourself and give yourself a chance to show yourself.

2.4 accumulated experience in project management, product design, and team management.

3. key difficulty points of the project:
3.1 when the project is in its initial stage, the scenarios and requirements are not too clear. I have summarized some of the requirements and need to collect them. The design needs to be discussed, met, and summarized with many leaders.
3.2 design of the overall framework structure
3.3 Development Plan arrangement: two colleagues are more experienced than me, have a high position, have many daily tasks, make development tasks difficult to arrange, and make resource coordination difficult
3.4 leaders are under great pressure on the project
3.5 when other functions are involved, the development progress is easily affected.

4. Your own problems:
4.1 I do not have a deep understanding of project-related technical applications, and I feel very confident.
4.2 Insufficient project management experience
4.3 self-confidence has been hit very low recently
4.4 impatient personality

I listed the above parts and gave a general summary of the existing, existing, and necessary tasks of the entire project. I listed a plan myself:
1. Collection of scenarios and requirements
1.1 learning from popular products in the industry
1.2 organizations 2 ~ 3 group discussions and meeting minutes
1.3 prepare the requirement documents, and the project team and leaders should confirm the requirements in a unified manner
2. Detailed Design
2.1 prepare a design draft by yourself
2.2 The project team has organized two discussions to draft a design draft.
2.3 determine the final draft for the first draft of the design and discussion by the leaders and architects.
3. coding implementation
3.1 identify the key points and compile the project
3.2 coding implementation based on the project
3.3 Weekly Review of the project team (email and weekly meeting)
3.4 project weekly report and project progress summary and compilation report
3.5 communicate and confirm with the relevant project team on the message platform and scheduled tasks
4. Test
4.1 Functional testing, unit testing, and performance testing
4.2 promptly fix bugs and submit build
5. project delivery
5.1 submit related product patches, installation programs and instructions
5.2 submit the Completion Report
5.3 project report and summary.
6. Activities

The above is a plan I listed myself. I feel a lot of dissatisfaction. Please give your comments and point out the incorrect points. Thank you.



 

 

Contact Us

The content source of this page is from Internet, which doesn't represent Alibaba Cloud's opinion; products and services mentioned on that page don't have any relationship with Alibaba Cloud. If the content of the page makes you feel confusing, please write us an email, we will handle the problem within 5 days after receiving your email.

If you find any instances of plagiarism from the community, please send an email to: info-contact@alibabacloud.com and provide relevant evidence. A staff member will contact you within 5 working days.

A Free Trial That Lets You Build Big!

Start building with 50+ products and up to 12 months usage for Elastic Compute Service

  • Sales Support

    1 on 1 presale consultation

  • After-Sales Support

    24/7 Technical Support 6 Free Tickets per Quarter Faster Response

  • Alibaba Cloud offers highly flexible support services tailored to meet your exact needs.