Audit report on some of the airport construction in Beijing, February 14 (reporter Cui Peng) The Audit Commission issued the sixth 2011 Bulletin, published the "10 Provinces and cities part of the airport construction audit survey results." The audit found that 359 contracts for 23 airport projects (19.7% per cent of the total number of test items 1817) were subject to a breach of the tendering process, such as open tendering, involving an amount of 1.938 billion yuan. "Eleven-Five" period, 10 provinces and cities in a total of new and expanded airport 53 from May 2010 to July, the Audit Commission on Shanxi, Inner Mongolia, Heilongjiang, Fujian, Guangxi, Chongqing, Sichuan, Yunnan, Shaanxi and Xinjiang, 10 provinces, autonomous regions, municipalities (hereinafter referred to as 10 provinces and municipalities) the airport construction situation carried out a survey, The focus was on 31 airports. The audit found that during the "Eleven-Five" period, 10 provinces and cities were newly built and rebuilt 53 airports, Total investment of 68.198 billion yuan, to the end of 2009 to complete the total investment of 32.375 billion yuan, the audit investigation of the 31 airport construction projects total investment of 62.116 billion yuan, the total investment 30.573 billion yuan, accounting for 53 of the airport 91% and 94.4% respectively. The airport construction management is better overall, the airport development is steadily advancing audit investigation results show that "Eleven-Five-year" period, Shanxi, Inner Mongolia, Heilongjiang and other 10 provinces and municipalities and Civil Aviation Administration actively raise funds, issued a number of policies to support the airport construction and operation, the airport construction and management of the overall better, the Construction and operation have achieved some results. The main results include the following two aspects: first, the airport layout gradually improved, transport capacity has been greatly improved. "Eleven-Five" period, 10 new airport 18, the number of airports than "XV" at the end of the growth of nearly 30%, at the same time, the original 35 airports have been rebuilt and expanded, so that air transport capacity has been greatly improved, of which 23 after the expansion of the operation of the airport, 2009 passenger throughput reached 59.4 million people, Grew by 28% in 2008. In particular, Xinjiang Kanas, Inner Mongolia Erenhot, Heilongjiang Mohe, Yunnan Tengchong, Sichuan kangding, Guangxi Baise and Fujian Sanming, such as "old, small, edge, poor" regional branch of the new airport, and further improve the remote areas of traffic travel conditions, but also make the overall layout of the airport gradually improved. The other is that the airport construction has stimulated local regional economic development to some extent and improved the local investment environment. By the end of 2009, the central government invested more than 3.745 billion yuan to subsidize 25 airport construction, accumulated 23.743 billion yuan in investment, pulled local investment 5.898 billion yuan, created 59,061 jobs, and effectively promoted the steady and rapid development of regional economy. At the same time, airport construction has also played an important role in improving the local investment environment and promoting the development of related industries such as tourism. The audit found that there were 359 contracts in breach of the tendering procedure, such as open tendering, and the audit also foundSome important issues. Among them, the audit found that 23 airport projects 359 contracts (accounting for the total number of 1817 items 19.7%), there is no public bidding and other violations of the bidding procedures, involving a sum of 1.938 billion yuan. In addition, the audit found other problems:--Fuzhou, Quanzhou, Guilin, Erenhot and Manzhouli, 5 airports, such as long declaration, repeated applications and other ways to obtain more construction capital of 61 million yuan, for other projects in the airport expenditure, Daqing, Yulin, Urumqi and Chengdu and other 4 airport materials suppliers to evade taxes, In the settlement with the construction unit, the use of false invoices, involving the amount of 33 million yuan; the construction unit of the Chengdu Airport will subcontract the earthwork project to 13 natural persons, who evade the tax, and provide 223 "white stripes" in the settlement with the construction unit, involving an amount of 65 million yuan. --The construction contract signed by the bidding for the Field Road project of Daqing Saertu Airport is more than one times higher than the bid price (126 million yuan), and the project bidding and investment control is a mere formality. -5 airports were not approved in the EIA report, on the commencement of construction; 15 airports are put into operation without the acceptance of environmental protection; 7 projects did not build the sewage treatment system according to the original design requirements, some of the sewage produced by the airport directly discharged into rivers or farmland, there is a pollution hidden danger.
The content source of this page is from Internet, which doesn't represent Alibaba Cloud's opinion;
products and services mentioned on that page don't have any relationship with Alibaba Cloud. If the
content of the page makes you feel confusing, please write us an email, we will handle the problem
within 5 days after receiving your email.
If you find any instances of plagiarism from the community, please send an email to:
info-contact@alibabacloud.com
and provide relevant evidence. A staff member will contact you within 5 working days.