Note: The Development Management Checklists-series of articles are transplanted from my iteye blog. The Development Management checklists column will be updated directly in the future.
This article mainly aims to check your understanding and usage of the scrum Sprint plan meeting,
Through this article, you can check1. process and steps of your scrum Sprint plan MEETING2. output results of the MeetingSprint
design, including login registration interface, product information interface, user feedback interface and so on, it takes about 30 hours of working timeGroup Chen Zhili: Background management, including the establishment and connection of the database, the update of the quantity of goods, it takes about 20 hoursGroup One: Further market research and user demand analysis, takes about 15 hours of timeCrew Zhao Yonghen: Software Testing and maintenance takes about 8 hoursV. Daily STANDING meeting
Time
Date
Place
Job
18:40
5.21
Nine real
Integrated Network Assistant!
6:49
5.22
~
Change Solution Integration!
Difficulties encountered: Last night, the integration of the pie failed, many of the problems were never thought before. Think that the class are added to the new project, the Lib package is directed in, draw a new interface with the original ID value, and then build on the line. This morning can only
part of the sixth assignment according to the progress of the project
Learn the UML Diagram and the building method to learn about the tools required for blogging and design.
problems encountered: a database field with a length exceeding the limit error causes an insert exception, and some hidden bugs require multiple tests to discover. When you join a group, the request fails, and there is no error returning information that needs to be parsed from the logical layer of the code.
Complete and publish Summary blog, sixth chapter of building Law, learning UML diagram
Wu Jingan
Unit testing of completed functions
Improve the test results of completed functions, design test cases for the function of the next step plan implementation of the meeting
Hu Zhiquan
Complete part of the sixth assignment according to the progress of the project
Learn UML diagrams, Learn the tools your blog and design requires.
problems
Team Name: Polygonum multiflorumProject confirmation: "Ordering System"Project background: This ordering system is for the restaurant development of the ordering system, in order to facilitate the guests to the store can directly place orders, because in the usual time is the waiter to write a menu for guests, guests sometimes think more long, but the waiter can not directly leave to do other services (this is not very polite ~). So this app is for the convenience of guests and restaurants, how
Team Name: Polygonum multiflorumProject confirmation: "Ordering System"Project background: This ordering system is for the restaurant development of the ordering system, in order to facilitate the guests to the store can directly place orders, because in the usual time is the waiter to write a menu for guests, guests sometimes think more long, but the waiter can not directly leave to do other services (this is not very polite ~). So this app is for the convenience of guests and restaurants, how
Note: The Development Management Checklists-series of articles are transplanted from my iteye blog. The Development Management checklists column will be updated directly in the future.
This article mainly aims to check your understanding and usage of scrum Sprint plan meeting 2,
Through this article, you can check1. process and steps of your scrum Sprint plan meeting 22. Results of scrum
Listener Listener
Preface: wrote an article about filter: http://tianweili.github.io/blog/2015/01/26/java-filter/, now another listener, Filter and listener are often used in projects, and clever use can achieve a multiplier effect. So summarize the usage of the two.
Original link: http://tianweili.github.io/blog/2015/01/27/java-listener/
1. Definition and function of listener
Listener Listener is a functional component that automatically executes code when a application,session,request three o
1. Scrum plan MEETING
Before each sprint starts, you need to hold a Sprint plan meeting. The meeting time is generally 4 ~ 8 hours, participants include product owners, scrum masters, scrum teams, and others of interest, such as managers and customer representatives.The product owner selects high-priority tasks from the product backlog and works with the scrum team to determine how many features are requi
team blog
team GitHub
Second sprint questions and suggestions
hgf520
Regionalcrimeunit
xjy-gg
goidenbubble
No jobs submitted for the second sprint
liezhihua
LWHTF
No project progress control, blog/github follow up not in time
caicaihong
RaiCai
The Sprint Review Conference has long been an important part of scrum, a mechanism for the team to get feedback on the product increments that are delivered by the iteration. At the Sprint review meeting, the product owner determines the priority of the next sprint's requirements based on the feedback received.So, is the sprint review now obsolete?Ten years ago,
For more than a year, we've been using Ibm®rational team concert™ to support our Scrum teams, enjoy its features, coexist with its shortcomings, and develop its next version. Using the IBM Rational Team concert V2,jazz and the Rational Group concert teams can make significant improvements to Scrum and agile assessment, planning support delivery (not to mention more improved WEB clients and many other new features).
Sprint Planning
As we have used IB
In my previous introduction, I described the relationship between release, sprint, and story. Reference: several meetings in scrum management and our practices
To put it simply, a release can include several sprints, and a sprint contains several story. Of course, a story can span multiple sprints or release. But what about the version? In practice, we need to use the GIT tag pairCodeTo ensure that all th
In the past few monthsSprint plan MEETINGIt will take several minutes to name the current sprint. It is very interesting to review it.--- Agile genie
Let's take a look at the sprint name from project:
Sprint1 --- "the big con"
Sprint2 --- "Breakout"
Sprint3 --- "hours to doom day"
Sprint4 --- "the big end"
Sprint5 --- "The Dragon Warrior"
Those who are familiar with Garrison's death squad will be ve
Introduced:
For story, an important measure of its size is story point, which is not equivalent to the function point in the software workload assessment, because story is simply a rough relative estimate of the size of the story, and function Point is used to measure the exact size of a functional module and to participate in the calculation of the formula, which is clarified here.
The estimation of story point is a very deep learning, and we cannot be careless, because if we estimate less, i
1. Start a new sprint:Starting and ending: 2016.6.1~2016.6.14Follow the procedure below
Product Backlog: Continue down refinement
Sprint Planning meeting: Determine the goals to be completed for this sprint
Sprint Backlog: What to do with a new sprint
Mission claim
1. Start a new sprint:Starting and ending: 2016.6.1~2016.6.14Follow the procedure below
Product Backlog: Continue down refinement
Sprint Planning meeting: Determine the goals to be completed for this sprint
Sprint Backlog: What to do with a new sprint
Mission claim
mainactivity is a main class that inherits from the flashlight class. An inherited list of three nodes is formed at this time. The Baseactivity class is mainly used for initialization;Today's task: realize the dynamic layout of flashlight;Tomorrow's goal: to achieve the dynamic layout of the flashlight;5.12Yesterday completed: Activity_main.xml modified, the use of the framework layout, control the level of display, to achieve the effect of overlay display;Today's task: realize the dynamic layo
Introduced:
One of the first and most important activities for an iterative cycle sprint is the sprint Setup meeting. At this meeting, we will mainly explore some of the story that we need to accomplish in this sprint, and what the specific requirements of these story are. In fact, our company is taking the offshore development model, in which we have a time dif
The content source of this page is from Internet, which doesn't represent Alibaba Cloud's opinion;
products and services mentioned on that page don't have any relationship with Alibaba Cloud. If the
content of the page makes you feel confusing, please write us an email, we will handle the problem
within 5 days after receiving your email.
If you find any instances of plagiarism from the community, please send an email to:
info-contact@alibabacloud.com
and provide relevant evidence. A staff member will contact you within 5 working days.