Just learned a lot, before doing a lot of data center wiring project, contact a lot of users. For the next line and the way to go, as a wiring factory technicians, often encountered in the project users in this regard and thinking, but also I often think about the problem. In the past in the project, my personal experience briefly introduced, of course, shieber this side of the comments, many aspects are agreed.
First of all, from my project experience, now on the line more and more, but the next line is also some. I think the upper and lower line should consider the application of the occasion has a different situation.
Second, it can be said that now the line is a trend, because the next line and floor air-conditioning static pressure box is related, now tend to the static under the floor, one is more and less cable, even in addition to the weak line cable on the line, there are strong wire cable on the line, the other one is the floor higher, I see 40 centimeters , 60 centimeters, or even higher, you can walk under the floor.
Again, conversely, if you consider the cabling, then the high level of construction requirements is very high. We have encountered a data center project, the upper line has three-storey bridge, for the three-storey bridge emissions and trends, in the implementation of the feeling is quite complex. In my opinion, the complexity is very high for multilayer up-line overhead bridge system, from design to installation implementation, and finally to the user in maintenance operation.
Again, on the line, assuming that the future users to increase some cable, because the requirements of beauty, is not able to arbitrarily pull, so laying and finishing requirements are high, because it is open. Conversely, the next line, in a project, once saw a tool, you can stretch, used in the floor after the separation layer, threading under the floor, feeling that very convenient.
But for the upper line, the bridge is not easy to thread, ladder up very high, and the previous lines themselves in the top of the sorting is already very good, for the new cable, on the line is also a big challenge.
Again, from the maintenance point of view, there is a very important premise is to be concise, easy to identify. Therefore, we hope that this cable laying, strapping to do very beautiful, because the beautiful things, people in the maintenance, care of the time is easier to identify, but also willing to spend time to add new cable finishing well. For aesthetic requirements, whether the walk line is on the floor or under the floor is the same.
More Wonderful content: http://www.bianceng.cn/Network/zhbx/
Some foreign data center project wiring, the floor opened after the line is very neat, you can do each line above the logo, see very clearly. From a neat and beautiful point of view, whether it is on the floor or under the floor should be the same, so easy to establish good maintenance, for the long-term use of users is beneficial.
At the same time to ask a question, is also one of the problems of thinking, the air-conditioning solution now has a closed program, such as two rows to seal it up, it may also be two cabinets inside the hot channel, may also be cold channel, called Cold Channel containment or hot channel containment. From the angle of wiring, this kind of closed program inside how to do open wiring, how to do aerial wiring? Is the overhead good, or to do the wiring under the floor?
Another problem, now the engine room inside the server room, there are storage rooms, minicomputer, mainframe computer room, these equipment is a monomer equipment, do not need to be placed in the cabinet, for this equipment wiring, whether it is appropriate to go on line?
Because at present for this kind of place is the suggestion floor to walk the line, has the floor to have the installment box below, the wiring to the floor area wiring box, a box can accommodate hundreds of pairs of fiber, the wiring is in place, this room future equipment may be gradually increased, and then through the jumper connection. How do you do this part of the line? This is all a problem. I think the upper and lower line each have advantages, the line is a trend, the next line or have its own characteristics, specific projects should be based on the actual needs of careful choice.
Finally, back to the management of the data center, creating a neat and beautiful environment is very important, such as a room is not beautiful, for the future management effectiveness is very helpful. So in the wiring management, whether it is on the line, down line, are very critical issues, including color management, logo management, should consider the establishment of a wiring management system to improve efficiency, assuming that each management wiring staff, performance improvement of 10%, overall look will be a great progress.