Serial number |
Date |
Time |
Item content |
Remarks (prerequisite and completion) |
Owner |
Completion status |
1 |
July 20 |
15: 00 |
Verify Email users again |
Pre-job: user verification (domain account/email account) |
Completed |
2 |
July 20 |
17: 11 |
Test the script for batch import of usersProgramVbs |
Task 1: Modify the preceding individual users and test the availability of the script in the test environment. In particular, when the script execution of the original user exists, the script function: change the password of the existing user, no user creates a user and generates a password. The test also found that the user in the script can use a Chinese name. |
Completed |
3 |
July 21 |
20: 39 |
Personnel group distribution list processing |
Task 2: Personnel Grouping and distribution list processing. |
Completed |
4 |
July 21 |
|
Adjust the DNS record of the email Intranet |
Pre-job: Stop the Internet mirapoint, change the DNS record to mail. Pre-job: The Intranet network path test is normal, including the Mail Gateway link. Post-task: rollback plan. |
Completed |
5 |
July 21 |
22: 58 |
Adjust the DNS record of the Internet Mail |
Direct the DNS record of the Internet mail to the external IP address of the company. Preconditions: the Internet network access test is normal, including the Mail Gateway link. Post-task: rollback Solution |
Completed |
6 |
July 21 |
Rollback Solution |
In case of a fault, you can roll back the fault. Change the Intranet DNS record back to email. Delete external IP address records from Internet DNS records |
No rollback solution used |
7 |
July 21 |
22: 56 |
NLB host record Adjustment |
Change email to the NLB record of mail. This NLB record has been tested in the email environment. Change the NLB record to mail in the NLB Cluster |
Completed |
8 |
July 21 |
22: 57 |
Modify default array database records |
Direct the default array database record email to mail |
Completed |
9 |
July 21 |
22: 59 |
Update the RPC client access records of the original email database |
Change the RPC record of the mail database on the mail1 and mail2 servers to mail. |
Completed |
10 |
July 21 |
23: 10 |
Verify the RPC access record of the email database |
Task 9 updates the RPC client access records of the original email database. |
Completed |
11 |
July 21 |
23: 11 |
Adjust the IIS redirect Host header record |
Task 7: NLB host record adjustment. Change the original test emailiis redirection Host header to mail prefix task to RPC client access record update |
Completed |
12 |
July 21 |
17: 40 |
Batch import user information |
Task 2: Verify the email user/batch import the user's script program vbs. |
Completed |
13 |
July 21 |
Add text information to the OWA Interface |
Text Content: "" |
14 |
July 21 |
17: 43 |
User's mobile phone number |
Task 2: manually add the user's mobile phone number |
Completed |
15 |
July 21 |
20: 10 |
Intranet Outlook client Test |
Test the connectivity test of the Outlook client and the mail sending and receiving test. Pre-tasks: verify the data by importing new user information (all tests with suffixes and no suffixes) |
Completed |
16 |
July 21 |
20: 15 |
Intranet OWA client Test |
Test the OWA client connectivity test and the mail sending and receiving test. The pre-task is verified by the imported new user information. |
Completed |
17 |
July 21 |
22: 20 |
Intranet Mobile Terminal Test |
Test the connectivity test and email sending and receiving test of the mobile client (Android, Apple IOS). The pre-task is verified by the imported new user information. |
Completed |
18 |
July 21 |
23:52 |
Outlook in the Internet environment |
Test the connectivity test of the Outlook client and the mail sending and receiving test. The pre-task is verified by the imported new user information. |
Completed |
19 |
July 21 |
23:54 |
Test the Internet OWA Client |
Test the OWA client connectivity test and the mail sending and receiving test. The pre-task is verified by the imported new user information. |
Completed |
20 |
July 21 |
23: 55 |
Internet Mobile Terminal Test |
Test the connectivity test and email sending and receiving test of the mobile client (Android, Apple IOS). The pre-task is verified by the imported new user information. |
Completed |
21 |
July 21 |
20: 29 |
Test email archiving and recall |
Test email archiving and recall Functions |
Completed |
22 |
July 21 |
23: 20 |
Hybrid scenario test (intranet for sending and receiving Internet and Internet for sending and receiving intranet) |
Test the connectivity test and mail sending and receiving test of the Intranet and Internet mutual sending and receiving of various clients. The pre-task is to verify the information of new users imported. |
Completed |
23 |
July 21 |
|
The administrator of a subordinate company modifies the user information through OWA. |
Web-based permission testing for OWA and virtual machine testing |
Completed |
24 |
July 21 |
20: 43 |
Calendar and reminder function test |
Test the functions of outlook and mobile calendar and reminders. |
Completed |
25 |
July 21 |
0: 52 |
Email CAS high availability test |
Test the high availability of email cas, and test the high availability of email service shutdown and service shutdown of mail1 or mail2. |
Completed |
26 |
July 21 |
0: 33 |
High Availability test of email service |
Email server Dag availability, high availability test for mail service shutdown and service shutdown of mail1 or mail2 |
Completed |
27 |
July 21 |
1: 20 |
Test the barracuda device of the Mail Security Gateway |
However, when sending and receiving emails, check whether there are test records in the gateway and test the load monitoring. |
Completed |
28 |
July 21 |
1: 55 |
Email activation notification |
Send email activation notifications to all users, and write the notification text in advance. |
Completed |
29 |
July 21 |
17: 43 |
Mailbox quota |
Major leaders: 500 m, Ministers: 200 m, general employees: 100 m. No Pipe Company quota |
Completed |