First, the preface
As a system engineering, integrated cabling is an indispensable part of modern intelligent building. In this paper, integrated wiring as an independent project, starting from the project management, talk about the integrated wiring system engineering in the construction process should be how to carry out scientific and effective management
From the construction point of view, the integrated wiring as an independent system, it in the overall construction of the project deployment and management objectives under the guidance of the formation of its own project management plan and objectives, in accordance with its prior design, to meet the corresponding level and quality requirements, completed on schedule to the owners to use.
Wiring project signed contract, received the project headquarters (or construction side, supervision) "Project Construction Admission Notice" date, the integrated wiring Project Department was established and entered the project site ready to start construction.
Ii. organization of personnel arrangements
The establishment of the project department shall make corresponding personnel arrangements: (according to the actual situation in the field, if the project is small, one person can undertake two or three jobs)
Project Manager: Has the experience of management and implementation of large cabling system project, supervises the implementation of the whole project, is responsible for the progress of project implementation, and is responsible for solving all kinds of problems arising in the project implementation process. Responsible for the coordination with the owners and related personnel.
Technical personnel: The request has the rich project construction experience, to the project implementation process appears the progress, the technology and so on, promptly reports the project manager. Familiar with the engineering features, technical features and product characteristics of the integrated wiring system, and be familiar with the relevant technical implementation standards and acceptance standards, responsible for coordinating the system equipment inspection and engineering acceptance work.
Quality, material staff: required to be familiar with the project required materials, equipment specifications, responsible for materials, equipment and access to the library management and inventory management, to ensure the integrity of inventory equipment.
Safety officer: Requires a strong sense of responsibility, is responsible for patrol daily work safety precautions and inventory equipment materials safety.
Data clerk: Responsible for daily engineering data finishing (drawings, negotiation documents, supervision documents, engineering documents, completed materials, etc.).
Construction team personnel: bear the construction production, should have the corresponding construction capacity and experience.
(figure for the typical wiring Construction organization chart)