Task and review
After the project is created and assigned to a specified user, the Project Manager (Zhang) can log on to the Project Server Web page through PWA to view the tasks.
1. view the task
The user (EMPLOYEE 1) logs on to the PWA page, and the assigned task is displayed in the "task" list.
650) This. width = 650; "src =" http://s3.51cto.com/wyfs02/M01/3C/BE/wKioL1PDRtWS8zlTAANIsNgP3BA926.jpg "Title =" 1.jpg" alt = "wkiol1pdrtws8zltaanisngp3ba926.jpg"/>
In addition, you can see all the problems assigned to you in "problems", and of course you can see "risks"
650) This. width = 650; "src =" http://s3.51cto.com/wyfs02/M01/3C/BE/wKiom1PDRw7DnA6qAAH0wF2Wyac853.jpg "Title =" 2.jpg" alt = "wkiom1pdrw7dna 6qaah0wf2wyac853.jpg"/>
650) This. width = 650; "src =" http://s3.51cto.com/wyfs02/M02/3C/BE/wKiom1PDR5fxMBhjAATRI7nxYFA514.jpg "Title =" 3.jpg" alt = "wkiom1pdr5fxmbhjaatri7nxyfa514.jpg"/>
2. Complete the task
1) After the resource (employee B) completes the task, you can select the completed task name in the "task" list and click "Mark complete ".
650) This. width = 650; "src =" http://s3.51cto.com/wyfs02/M02/3C/BE/wKioL1PDR3KSiUAkAAQNngF3Bu4509.jpg "Title =" 4.jpg" alt = "wkiol1pdr3ksiuakaaqnngf3buw.9.jpg"/>
2) After the user marks "finished", the "working hours completion percentage" of the task changes to 100%, and then save as prompted.
650) This. width = 650; "src =" http://s3.51cto.com/wyfs02/M01/3C/BE/wKiom1PDR6qRqXaTAAQ4syAnLEs605.jpg "Title =" 5.jpg" alt = "wkiom1pdr6qrqxataaq4syanles605.jpg"/>
3) after the storage is complete, "Send status" is provided for approval by the Project Manager. The "Process status" of the job changes to "waiting for approval ".
650) This. width = 650; "src =" http://s3.51cto.com/wyfs02/M00/3C/BE/wKioL1PDR4OBSN3YAAQmOmwi-Eg035.jpg "Title =" 6.jpg" alt = "wKioL1PDR4OBSN3YAAQmOmwi-Eg035.jpg"/>
4) After logging on to the Project Manager (Manager Zhang), you can view the status of the task to be approved in "approval" on the quick navigation bar. Select the name of the approved task and click "accept. This completes the approval process of the project manager.
650) This. width = 650; "src =" http://s3.51cto.com/wyfs02/M02/3C/BE/wKiom1PDR7zxu2ZkAANr92Nvtqc885.jpg "Title =" 7.jpg" alt = "wkiom1pdr7zxu2zkaanr92nvtqc885.jpg"/>
5) You can enter encouraging text in the "confirm approval" dialog box. Notify the entire project working group.
650) This. width = 650; "src =" http://s3.51cto.com/wyfs02/M00/3C/BF/wKiom1PDR8OTKEHsAAMaiubHWQI280.jpg "Title =" 8.jpg" alt = "wkiom1pdr8otkehsaamaiubhwqi280.jpg"/>
6) after the project manager approves the task, the employee (employee B) performing the task will be able to see the latest Task status "completed" in the "task" list ", you can continue with other tasks.
650) This. width = 650; "src =" http://s3.51cto.com/wyfs02/M02/3C/BE/wKioL1PDR5yTNOcSAAPc7kmPvns273.jpg "Title =" 9.jpg" alt = "wkiol1pdr5ytnocsaapc7kmpvns273.jpg"/>