Requirements: Select a team of products, to the existing functions (reference user Requirements Specification and final release) WSB function decomposition to three sub-function, estimate the time required for each sub-function.
WBS decomposition is as follows
Function |
First-level sub-function |
Two-level sub-function |
Estimated time spent (hours) |
Administrator function Module |
Student Management |
Query function |
2 |
Teacher Management |
Remove a role |
1 |
|
Add a role |
1.5 |
|
Query role |
1 |
|
assigning permissions |
2 |
|
Edit role |
1.5 |
Teacher Function Module |
Personal information Management |
Edit personal Information |
1 |
Student Test Paper Management |
Publish Exercise Exercises |
2 |
|
Editing questions |
2 |
|
Check the results of the section |
1 |
Student Function Module |
Personal information Management |
Change Password |
1 |
Exam Management |
Online Exams |
2 |
|
Score Enquiry |
1 |
|
Online training |
3 |
The Gantt chart for the project task is as follows: The horizontal axis represents the duration, and the vertical represents the task.
Functional decomposition of the Golden State Warriors team project (plus Division work)