How to Set (create) milestones in a project

Source: Internet
Author: User

It's easy to createZero work periodProject is automatically displayed as a milestone.

For more details, refer to the project help:

  1. In"View"ClickGantt Chart".
  2. In the task to be changed (task: an operation with the start date and completion date. A project plan consists of tasks .) Of"Construction Period"Type0.
  3. Press enter.

    When you enter a zero-time period for the task (duration: The total range of valid working hours required to complete the task. Generally, the project calendar and resource calendar define the total amount of work time from the task start time to the completion time .) Microsoft Office Project 2003 displays the Gantt chart of the current day (chart: A part of the view or view that graphically represents the project information. For example, the Gantt Chart view consists of a worksheet and a chart pane, in which the task is represented as a horizontal bar chart .) A milestone is a reference point that represents a major event in a project and is used to monitor the project progress. Any task with zero construction period is automatically displayed as a milestone, or other tasks with any construction period can be marked as milestones .) Symbol.

Note

  • Sometimes, you need to track events outside of the project. If these events cannot be linked because they are not in the Project Plan (link: Establish dependencies between tasks in the project. A linked task defines the correlation between its start date and completion date. Establish connections between programs in OLE to update the data in other documents when changing data in one document .) You can create milestones in the project to represent them. For example, if you can start a task only after other companies complete the software applications you need, you can create milestones in the project to indicate the application's completion time and remind you to track its progress.
  • Some milestones may require a construction period. For example, your project is in a certain stage (phase: a group of related tasks that complete the main steps of the project .) There is an approval milestone at the end of, and you know that the approval process will last for one week. To mark a task as a milestone with more than 0 working days, click"Task information"And then click"Advanced"Tab. In"Construction Period"Enter the task duration, and then select"Mark as Milestone"Check box.

Contact Us

The content source of this page is from Internet, which doesn't represent Alibaba Cloud's opinion; products and services mentioned on that page don't have any relationship with Alibaba Cloud. If the content of the page makes you feel confusing, please write us an email, we will handle the problem within 5 days after receiving your email.

If you find any instances of plagiarism from the community, please send an email to: info-contact@alibabacloud.com and provide relevant evidence. A staff member will contact you within 5 working days.

A Free Trial That Lets You Build Big!

Start building with 50+ products and up to 12 months usage for Elastic Compute Service

  • Sales Support

    1 on 1 presale consultation

  • After-Sales Support

    24/7 Technical Support 6 Free Tickets per Quarter Faster Response

  • Alibaba Cloud offers highly flexible support services tailored to meet your exact needs.