Based on the decimal point of the unit of material, this article continues to explain the influence of the unit of material rounding on MRP.
This article briefly introduces the impact on MRP when the unit of material is set to an integer. The related operations are as follows:
TransactionsCodeMm01 maintains finished product zmto100,
The transaction code mm01 maintains the raw material zrh200, sets the unit to PC, and sets the batch type of raw materials to a two-week summary (2 W ),
Transaction code cuni, set unit PC to INTEGER (Icon 2)
Maintain the BOM of zmto100 for finished products, and set up a finished product to require 1.11 raw materials.
Transaction code md61 maintains independent requirements for finished products
Run MRP to obtain the following requirements for the components:
Number of finished products |
Number of components required for each finished product |
Number of required components |
101 |
1.11 |
= 101*1.11 = 112.11 |
101 |
1.11 |
= 101*1.11 = 112.11 |
The number of related requirements is automatically rounded up to 113
The batch type of raw materials is set to a two-week summary. Therefore, the number of two related requirements is summarized, and the number of purchase applications generated is 226.