Dependent requirements Ind. for individual and Coll. reqmts

Indicator determining whether the following requirements is allowed for the dependent requirements of the Materi Al

    • Individual requirements
      requirement quantities of the dependent material is stated individually.
    • Collective requirements
      requirement quantities of the dependent material is grouped together.
Use

You can maintain this indicator in the following places:

    • In the material master record
    • For the explosion type of the BOM item (in customizing to Basic Data in Define explosion Types)

The setting for the explosion type overrides this in the material master record.

Dependencies

If the material is assigned to a material type then does not allow quantity-based inventory management (Kmat type) in this Plant, you can set the indicator to individual requirements only.

If the stock is to being managed in sales order stock or project stock, the indicator must are set to one of The following options:

    • Individual and collective requirements
    • Individual requirements only

If a material managed in project stock was to being procured from another plant using a Cross-company-code stock transport ord Er, the indicator must is set to 2 (collective requirements) in the issuing plant because, in this specific conte XT, individual project stock management is not possible in both plants.

>>>>>>>>>>>>>>>>>>>>>>>>>>> >>>>>>>>>>>>>>>>>>>>>>>>>>> >>>>>>>>>>>>>>>>>>>>>>>>>>> >>>>>>>>>>>>>>>>

If you set individual indicator for both headers material and dependent material, then if sale order comes for the Qty, Then During MRP Run system would create a plan order with reference to sale order and for dependent material, system would p LAN dependent material as sale order relevant. System won ' t consider warehouse stock for that sale order.

In the your case, you can set the individual/collective indicator as 1 for dependent and no for Header material. Mostly This can is used for do to order scenario.

If you set the individual/collective indicator as 1 for the Header material, during MRP run system would not consider the E Xisting Warehouse stocks for the sales order, MRP would create Planned order against of sales order.

>>>>>>>>>>>>>>>>>>>>>>>>>>> >>>>>>>>>>>>>>>>>>>>>>>>>>> >>>>>>>>>>

Indicator = "1"---Mostly for kmat material (Kmat type) and Make-to-order scenario.

Indicator = "2"----

>>>>>>>>>>>>>>>>>>>>>>>>>> >>>>>>>>>>>>>>>>>>>>>>>>>>> >>>>>>>>>>>>>>>>>>>>>>>>>>> >>>>>>>>>>

What's the relevance of individual/collective requirement indicator from MRP4 view of material for finished product a s well as it sub assemblies in case of make to Stock planning strategies.

Answer:

Individual & Collective indicator plays a major role in MRP.

If you set individual indicator for both headers material and dependentmaterial, then if sale order comes for 100 Qty, then During MRP run Systemwill create a planned order with reference to sale order and for dependentmaterial, system Would plan dependent material as sales order relevant. Systemwon ' t consider warehouse stock for that sale order.

If You set collective indicator for dependent material System Willconsider warehouse stock for dependent MATERIAL.

MRP-4 as 1: In individual planning, this indicator is usedto display the dependent requirements of a component separately.

MRP-4 as 2: In collective requirements, this indicator is usedto display the dependent requirements of a component grouped together.

This Indicator was useful to control the planning of dependent requirementsif the main product was being planned with Strate Gy i.e.; MTO Process.


Marc-sbdkzIndicator controls whether individual or Collectivecustomer requirements planning is allowed for dependent requirements me Anslow level in BOM.

If you define individual requirements for explosion, dependent requirementsfor a component is shown individually on the S Uperior low-level code.

If you define collective requirements for explosion, required quantitiesfor the material is summarized independently of T He sales order.

In the MTO scenario, if you want to check the unrestricted raw materialstock when you run the MRP for sales order. Please check by selectingindividual/collective requirement as 2.

Please Note:

-If you selectindividualRequirement then system would not consideravailable the stock and generate proposals for every a single requirements. Also you'll find PR and Plan order with account assignment of Sales orderMD50).

-If you select collective requirement then system would not generateplanning proposals throughMD50. In this case you had Togo for individual MRP (md02/md03/md41/md42).

For FG stock You can assign to sales order throughmb1bBy412EMovement type.

MRP4-Dependent requirements Ind. for individual and Coll. Reqmts

Contact Us

The content source of this page is from Internet, which doesn't represent Alibaba Cloud's opinion; products and services mentioned on that page don't have any relationship with Alibaba Cloud. If the content of the page makes you feel confusing, please write us an email, we will handle the problem within 5 days after receiving your email.

If you find any instances of plagiarism from the community, please send an email to: info-contact@alibabacloud.com and provide relevant evidence. A staff member will contact you within 5 working days.

A Free Trial That Lets You Build Big!

Start building with 50+ products and up to 12 months usage for Elastic Compute Service

  • Sales Support

    1 on 1 presale consultation

  • After-Sales Support

    24/7 Technical Support 6 Free Tickets per Quarter Faster Response

  • Alibaba Cloud offers highly flexible support services tailored to meet your exact needs.