First, team members
Leader:
Cheng: http://www.cnblogs.com/chengqiqin07/
Members:
Zhiqiang: http://www.cnblogs.com/haoying1994/
Li Yu: http://www.cnblogs.com/Aliqiao/
Ii. planning of the meeting process
April 13, 2016 two o'clock in the afternoon, all the members of the wood and 15 317 held a team project planning meeting, at which we carried out a specific analysis of our project. The meeting process is as follows:
(1) Using the paper prototype method to the general analysis of our project, the interface is roughly depicted, the project is expected to contain 5 interfaces, namely the Welcome interface, weather interface, has a reminder interface, add reminder interface, reminder interface.
(2) Making task index cards and task Kanban
(3) Mission claim
(4) Project estimate
Third, Team backlog, task index card and task claim, project estimate
1, welcome interface--person in charge: Li Qiao
(1) Background, icon (estimated time: 1h)
(2) concrete implementation (timing jump) (Estimated time: 5h)
2. Weather interface--person in charge: Li Qiao
(1) Background, icon (estimated time: 1h)
(2) Weather conditions Import (estimated time: 20h)
(3) Specific code implementation (estimated time: 20h)
3, the existing reminder interface--person in charge: Cheng Qin
(1) Background, icon (estimated time: 1h)
(2) interface layout (estimated time: 2h)
(3) Realization reminder (Estimated time: 10h)
4, set the reminder interface--person in charge: Zhiqiang
(1) Background, icon (estimated time: 1h)
(2) interface layout (estimated time: 2h)
(3) Time selection Framework (estimated time: 5h)
(4) Reminder mode frame (estimated time: 5h)
(5) Reminder content (Estimated time: 10h)
(6) Setting the control (estimated time: 2h)
5, remind the interface--person in charge: Cheng Qin
(1) Background, icon (estimated time: 1h)
(2) Display weather, time (estimated time: 10h)
(2) Closing method (estimated time: 5h)
Iv. Task Kanban Photos