3.0-----------------------------------------------------
Steps of the SCRUM process 2:spring plan
1. Make sure the product backlog is organized.
2. Sprint cycle, a sprint cycle, length of two weeks, this semester also has three sprint cycle.
3. Determine the sprint target.
3.1 The product owner summarizes the product backlog, provides a general overview of the sprint goals, and tells the story that he considers most important. The 3.2 team discusses each story from the most important stories, estimating the time, sorting out the meaning of each entry, and splitting the backlog entry if necessary. All high-importance backlog entries are filled in with "how to demonstrate." 3.3 The team chooses the story to be put into the sprint based on productivity. 4. Split the story further into tasks. 5. Form the sprint backlog. Scrum Master is a big step, organizing everyone to work smoothly and in accordance with the scrum process. Requirements: Organize the results of 1,3,4,5 work into a blog post on the team blog. Closing Date: 2016.5.12 10 o'clock in the evening.
team Name: skinny don't eat fat
Team objectives: compounding and investment record projects continue to upgrade, development of targeted, functional focus of tool-based software
Team slogan: strive for the race
Role Assignment:
Product Owner: Chowa
Scrum Master: Ho
PM Project Manager: Practice Siming
One:Product Backlog:
Id |
Name |
Tmp |
Est |
How to Demo |
Notes |
1 |
Financial |
100 |
3 days |
Realization of the Web version, the realization of various functions of the specific calculation |
|
2 |
Account Login |
80 |
3 days |
Connect user registration information with a database |
|
3 |
UI interface Design |
60 |
3 days |
Beautify the interface, let more people like. |
|
4 |
Music |
40 |
2 days |
|
Add background music |
5 |
Labeling Investment Records |
70 |
3 days |
Connect user information with a database |
|
6 |
Insert Ad |
30 |
3 days |
|
Insert Advertisement, |
two: determine sprint Goals:
3.1
First of all, our original compounding program was programmed with C, so it is imperative that the compound interest function be fully implemented in Java. Our first spring plan was to fully show the functionality of compound interest in Java, and then the second spring plan was to connect the program to the database, increase the login function of the account, save the information, and beautify the UI so that the user could enjoy the tool at first glance.
3.2
1. The process of compounding C is implemented in Java, which is the precondition for our product backlog, which is estimated to be possible one day.
2. Using the technology learned to connect the process of compounding with the database, which is the basis for the production of web-based database, but also to add the function of account landing, saving information, which is also needed to use the database. Estimated time: 4-6 days.
3. Beautify the compound-computing interface, including inserting background images, such as the ability to add music. Estimated time: 3-4 days.
Three: Sprint Backlog:
Team Blogs and ratings
Practice Simin: 19
Chowa: http://www.cnblogs.com/luoliuxi/
HO: http://www.cnblogs.com/40heyuming/
Sprint 3.0