First, the team meeting plan
In the short term through further market research and demand analysis, more accurately grasp the user's needs, determine the overall software function direction. Based on the knowledge and skills that the team members are good at, carry out the initial task assignment and implement the basic framework of the software.
Ii. process of Team meeting
Our team of four in this Wednesday three o'clock in the afternoon in the foundation of a group meeting, first of all the software will be implemented in a specific analysis of the functions, and then the entire project backlog was combed, and finally through the voluntary principle of the work to claim.
Third, the team backlog
1, the user interface design, including login registration interface, commodity information interface, user feedback interface and so on.
2, background management, including the establishment and connection of the database, the update of the quantity of goods.
3, further market research and user needs analysis.
4, software testing and maintenance.
Iv. Job Claim
Group leader Tan Wei: User interface design, including login registration interface, product information interface, user feedback interface and so on, it takes about 30 hours of working time
Group Chen Zhili: Background management, including the establishment and connection of the database, the update of the quantity of goods, it takes about 20 hours
Group One: Further market research and user demand analysis, takes about 15 hours of time
Crew Zhao Yonghen: Software Testing and maintenance takes about 8 hours
V. Daily STANDING meeting Venue: 80 Square, Time: 7 a.m.
Spring Sprint Planning Meeting