Absrtact: Luo said that the capacity of the hammer handset is worse than the worst result in the plan, it may take several weeks to reach the level of 1800 units per day. In the capacity and quality problems of the start-up companies Hammer Technology Sunday External said, hammer cell phone capacity
Luo said the hammer phone's capacity is worse than the worst in the plan, and it could take weeks to reach 1800 units a day.
In the capacity and quality problems of the start-up companies Hammer technology Sunday Foreign said, hammer cell phone capacity is seriously inadequate, can not be scheduled on time to pay the 300 yuan subscription to the user shipments.
"The last 10 days are the hardest days since the company was founded, and our capacity is worse than the worst in the plan," hammer Technology said in an email to Tencent technology.
Confident Hammer Technology CEO Luo has been in trouble lately, bad news never left hammer technology. July 8, the jump-ticket has been a long time of the hammer phone officially on sale, but the first day of sales less than 1000 units. Then, some customers who received the goods reflect that there are serious problems in product quality. One of the most exaggerated is that there is no protective glass outside the rear-mounted camera of the phone.
A domestic brand mobile phone enterprise market leader told Tencent technology, the general handset manufacturers in the first few batches of goods need to be in raw materials, production, packaging more than one link to test, so the problem may be very small. The problem of having no lens glass like a hammer is certainly a matter of artificial.
Hetao, general manager of the former BYD Communications Terminal Division, commented on his microblog, never having customers tolerate a failure rate exceeding 1%. In fact, such a crisis is not common in the mobile phone industry, especially for Luo, which has claimed to have a harsh demand for the craft, and its "craftsman" image is rapidly collapsing.
For product problems, hammer technology responded that it had strictly walked through the P1 to P4 of the complete engineering machine stage. However, after the beginning of the production of production lines from the lack of running-in, workers on the new model assembly operation is not skilled, material initial supply instability, quality control standards are not completely unified. The hammer technology unification calls it "the constraints of complex factors".
According to the feedback from the production line, the current production capacity of the hammer at the best hundreds of units a day, bad time may stop the whole production line adjustment.
Foxconn's management has added more experienced production managers to the problem, but Hammer technology says, "so far, there are still two key components that have low yield." In other words, to achieve the level of Nissan 1800 units, it may take several weeks, and digest the existing orders, it may take several months.
In the mail, Hammer Technology announced a series of adjustments to be made: Provide refunds to customers who have already paid the advance payment, and receive reminders for their payments; 300 of the value of the user has paid a prepayment of 300 yuan hammer technology online store cash coupons can be purchased in late October, the next day, the way to cancel the
However, the hammer users may not be able to wait, they are fleeing. Hammer technology in the Mail said that the number of return to the singular than the usual increase of more than 100 units.